PJM Plans for 18,500 MW Shortfall in Electricity Through 2028
Last week, on Halloween Day, officials from the PJM Interconnection presented a plan to make up for the retirement of fossil fuel generators and increasing demand on the way over the next five years. The plan includes 72 proposals from FirstEnergy, Dominion, and other companies designed to meet future power needs --- for a total price tag of roughly $5 billion. Here is a startling admission from PJM made as part of its announcement: There will be a 7,500 megawatt (MW) increase in demand from now until 2028 due to data center additions to the system in Virginia and Maryland. At the same time, more than 11,000 MW of fossil fuel generation across the PJM footprint of 13 states and Washington, D.C., have or are being retired. Add the two together, and you get a delta of 18,500 MW that we need to cover somehow. Yikes!