PA DEP Permit Delays Causing Slowdown in New Marcellus Drilling

| | |

Delays in turning around permit applications for new Marcellus drilling is hurting the industry, according to the Marcellus Shale Coalition (MSC). MSC president Dave Spigelmyer says lack of certainty in the PA Marcellus means more drilling goes to neighboring West Virginia and Ohio–even to Louisiana. The PA Dept. of Environmental Protection (DEP), responsible for reviewing and issuing permits, sounds somewhat defensive about their lack of performance, blaming delays on staff shortages, staff turnover, and “enhanced scrutiny of permit applications.” The Pittsburgh office now takes over 200 days (over 6 months!) to process an erosion control permit–up from 139 days in 2015. Simply not acceptable…