CNX Midstream Sues Contractor for Walking Away from Pipe Project
On Monday, CNX Midstream sued West Virginia contractor Ronald Lane Inc. claiming the contractor "without warning or justification ceased work on the Project and abandoned the Project," the Project being a package of water and gas pipelines in Greene and Washington counties in PA. And that, "Lane informed [CNX] that Lane intended to redirect all of its forces and efforts to other projects that Lane considered to be more profitable than the Project. Lane made it clear to [CNX] that Lane had no intention to perform any more work on the Project." Lane was the winning bidder for the Project in late 2017 at a total cost of $7.1 million. According to the lawsuit, CNX claims Lane began construction in March and abandoned the Project in June.