Report Says Virginia DOES have Say in Pipeline to Feed Power Plant

| | |
Proposed Chickahominy pipeline route (click for larger version)
MDN first told you about plans to build the Chickahominy Power Station, a 1,650 megawatt state-of-the-art natural gas-fired power plant planned for Charles City County (near Richmond, Va.) in June 2018 (see Huge New Marcellus-Fired Power Plant Coming Near Richmond, VA). In September of this year, the Chickahominy project asked the Virginia State Corporation Commission (SCC), which oversees intrastate pipelines for utility companies, to excuse itself from regulating and overseeing the construction of a pipeline that will feed the Chickahominy power plant (see Va. Power Plant Says State Doesn’t Need to Approve Feeder Pipeline). A state Corporation Commission hearing examiner issued a report yesterday recommending the commission’s three judges reject that request. In other words, SCC does have the right and responsibility to regulate the pipeline.

To view this content, log into your member account. (Not a member? Join Today!)