DOE Orders Philly Gas-Fired Power Plants to Stay Online 3rd Time
U.S. Secretary of Energy Chris Wright issued an emergency order on November 25 directing PJM Interconnection and Constellation Energy to keep Units 3 and 4 at Pennsylvania’s Eddystone Generating Station (near Philadelphia, in Delaware County) operational through the winter. Effective from November 26, 2025, to February 24, 2026, the mandate aims to ensure grid reliability following PJM's record winter demand in January 2025. This directive follows two previous orders that kept the aging, dual-fuel units online to support energy security during summer heatwaves. The DOE asserts that despite planned retirements, these 380-MW units remain essential for stabilizing the regional power supply. Big Green is unhappy.To view this content, log into your member account. (Not a member? Join Today!)