Homer City Update: First Turbine Set, Amazon Plan Now Under Review
The Homer City Energy Campus in Indiana County, PA — the largest natural gas-fired power plant under construction anywhere in the U.S. — just ticked off a few nice milestones. Construction contractor Kiewit marked one year on the job, the workforce has topped 2,000, and the first of seven giant gas turbines is now sitting on its foundation. Meanwhile, Amazon's plan to build 36 data centers next door is officially on the county's review clock; the Department of Environmental Protection (DEP) just held a hearing on the plant's water discharge permit, and the usual suspects are still fighting the plant's air permit. Here's where things stand.To view this content, log into your member account. (Not a member? Join Today!)