Is PJM Giving Data Centers the Heisman with Connection Proposal?
There is a disagreement brewing between those who operate the PJM Interconnection power grid and Big Tech, including Amazon, Google, Microsoft, and others, regarding the issue of adding data centers to the PJM grid. PJM recently proposed a fast-track stakeholder process to develop rules by the end of the year for interconnecting data centers to its system while ensuring the region has enough power supplies. The proposal would treat new data centers over 50 megawatts (MW) as "non-capacity-backed load" (or NCBL). Under the proposal, PJM could curtail (reduce or cut off) power deliveries to data centers with NCBL status before the grid operator moves to pre-emergency load curtailments for other electricity users. Big Tech doesn't like it one little bit.To view this content, log into your member account. (Not a member? Join Today!)