At last check in March of this year, Dominion’s Cove Point LNG export facility, being built in Maryland, was 24% done (see Cove Point LNG Export Plant Now 24% Complete, Rapid Progress). We’re not three months later and that number is now 38% done. No wonder the odious Sierra Club and other Big Green groups are trying so hard to block work on it! Dominion just filed a monthly status and progress report (full copy below) for Cove Point and they report the facility is 38% built. They also report the engineering is about done (99.8% complete) and equipment purchases are also done (99% complete). This is refreshingly good news. There is nothing stopping the facility now…