ME2 Construction in Lebanon County Stopped for 50 Gal Mud Spill
The Pennsylvania Dept. of Environmental Protection (DEP) has just shut down further drilling for the Mariner East 2 Pipeline project at Snitz Creek in Lebanon County, PA because of a 50 gallon spill of non-toxic drilling mud. This isn’t the first time the DEP has stopped underground horizontal directional drilling (HDD) work at Snitz Creek. Last November they did the same thing for a piddly 1 gallon spill (see PA DEP Shuts Down ME2 Drilling in Lebanon, PA for 1 Gal Mud Spill). In the parlance of today, leaking 50 gallons of drilling mud into Snitz Creek is a nothing-burger. Biased reporters like those at PBS StateImpact Pennsylvania make it out to be the environmental crime of the century. There’s more environmental damage from overfilling a gas tank at the local Sheetz that spills two gallons of gasoline onto the pavement than there is from spilling 50 gallons of non-toxic kitty litter (or toothpaste, or lipstick) into Snitz Creek. But there you go. Sunoco voluntarily reported the incident, and was promptly shut down at that site until further notice. Meanwhile, a few weeks ago a farmer in nearby Lancaster County spilled 100,000 gallons of manure into two creeks–with zero consequences. Why didn’t the DEP shut down the farm?…
Read More “ME2 Construction in Lebanon County Stopped for 50 Gal Mud Spill”

Last week MDN reported that due to underground horizontal direction drilling (HDD) in Chester County, PA for the Mariner East 2 (ME2) Pipeline project, a third sinkhole had developed. ME2 is being built close to the existing Mariner East 1 (ME1) pipeline. The sinkhole exposed a portion of the ME1 pipeline to the open air, which is why the head of the state Public Utility Commission (PUC) temporarily shut down the propane and ethane flowing through ME1 (see
A third sinkhole related to Mariner East 2 pipeline work and the uncovering (and subsequent shutdown) of the Mariner East 1 pipeline has some folks in Chester County, PA stirred up and rather grumpy (see 
In February, Sunoco Logistics Partners agreed to pay a massive (historically high) $12.6 million fine to the PA Dept. of Environmental Protection (DEP) for “permit violations related to the construction of the Mariner East 2 pipeline project” (see
Earlier this week Energy Transfer Partners (ET), one of the country’s largest midstream (pipeline) companies, released an update covering fourth quarter and full year 2017 results. As part of that update, the muckety-mucks from ET held an analyst conference call (yesterday). On that call they not only discussed what happened in 2017, but what is happening and will happen in 2018. ET, in case you didn’t know, is builder of both the monster Rover Pipeline project (from PA, WV and eastern OH through OH and into Michigan), as well as the Mariner East 2 (ME2) pipeline (NGL pipeline from eastern OH across the entire length of PA to the Marcus Hook facility near Philadelphia). We learned some important information from yesterday’s update. While the good news for both the Rover and ME2 is that they will both soon be fully operational, the truth is, both are delayed from their originally intended “in-service” dates. In the case of Rover, the new news delivered on yesterday’s conference call is that full operation of the entire length of Rover Pipeline, which will be capable of flowing up to 3.25 billion cubic feet per day (Bcf/d) of natural gas along its entire length, won’t happen until sometime in the second quarter 2018–that is, by the end of June. This is the first time ET has admitted full operation of the Rover pipeline will not be ready by end of March. However, to put this news in perspective, much of the pipeline is already done and currently flowing 2 Bcf/d–even as you read this. As for ME2, following an already-admitted delay until end of 2Q18, ET yesterday said it is keeping their estimate that the pipeline will be up and running by end of June, even though the project just came through a one-month construction shut down imposed by the PA Dept. of Environmental Protection. After ET (i.e. Sunoco Logistics Partners) paid a $12.6 million ransom (“fine”), the DEP relented and allowed it to restart construction. The one-month construction hiatus has not, according to officials, delayed the in-service date for ME2. Cool! Below is ET’s 4Q & full 2017 update. First up are ET comments about Rover and ME2…
Yesterday MDN brought you news that Uwchlan Township (Chester County, PA) has filed a lawsuit in an attempt to stop construction of the Mariner East 2 Pipeline (ME2) through portions of the town, claiming the pipeline violates a town ordinance for “setbacks”–how far the pipeline is located from buildings and other structures (see
We understand why folks in Uwchlan Township (Chester County, PA) may be upset with Sunoco Logistics and the Mariner East 2 NGL pipeline that’s crossing through their area. Last summer drilling work for the pipeline in Uwchlan created cloudy well water for some residents (see
In what can only be considered a government shakedown, Sunoco Logistics Partners agreed last week to pay a massive (historically high) $12.6 million fine to the PA Dept. of Environmental Protection (DEP) for “permit violations related to the construction of the Mariner East 2 pipeline project” (see
Last week MDN brought you the news that Sunoco Logistics Partners had agreed to pay a massive (historically high) $12.6 million fine to the PA Dept. of Environmental Protection (DEP) for “permit violations related to the construction of the Mariner East 2 pipeline project” (see
In what can only be considered a government shakedown, Sunoco Logistics Partners has agreed to pay a massive (historically high) $12.6 million fine to the PA Dept. of Environmental Protection (DEP) for “permit violations related to the construction of the Mariner East 2 pipeline project.” The fine, along with a “stringent compliance review” going forward, gives the DEP enough confidence to allow Sunoco to resume construction on the ME2 project, which has been halted since January 3rd (see 
In early January, the Pennsylvania Dept. of Environmental Protection (DEP) told Sunoco Logistics Partners to suspend all work on the $2.5 billion Mariner East 2 (ME2) NGL pipline–from one side of the state to the other (see
You may recall our story about the daughter of a Huntingdon County, PA landowner who took to a tree on her mom’s property in March 2016 in order to illegally stop crews working on tree clearing for the Mariner East 2 pipeline (see