NFG Asks FERC for Extra 3 Yrs to Build Northern Access Pipe in NY

Four years ago National Fuel Gas Company (NFG) proposed and filed to build the Northern Access Pipeline project–a $500 million project that includes building 97 miles of new pipeline along a power line corridor from northwestern Pennsylvania up to Erie County, NY. The project also calls for 3 miles of new pipeline further up, in Niagara County, along with a new compressor station in the Town of Pendleton (also in Niagara County). The Federal Energy Regulatory Commission (FERC) granted final approval for the project in February of 2017 (see NFG’s Northern Access Pipe in NY/PA Gets FERC Approval). However, in April 2017, the New York Dept. of Environmental Conservation (DEC) ruled against granting the project stream crossing permits, effectively killing it, at least for now (see Cuomo’s Corrupt NY DEC Blocks NFG Northern Access Pipeline Permit).
Read More “NFG Asks FERC for Extra 3 Yrs to Build Northern Access Pipe in NY”

Another bump in the road for National Fuel Gas Company and their Northern Access Expansion pipeline project. Not a major hurdle. Not an apocalypse. Not the end of the line. A bump. The Appellate Division of New York State Supreme Court (in NY, Supreme Court is a low court, one step up from county court), overturned the decision of the lower Supreme Court granting NFG the power of eminent domain to build Northern Access, a project not scheduled to get built until 2022. The attorney who won the case against NFG proclaimed without eminent domain, “The pipeline is dead.” We say he’s dead wrong.
We’re not much of a fan of the federal Environmental Protection Agency–especially the agency under the jackboots of the Obamadroids. The Obama years saw egregious abuses and wild new regulations that tried to stamp out the fossil fuel industry. In March 2016, we told you about a new “voluntary” program set up by the Obama EPA called the Natural Gas STAR Methane Challenge Program (see
Last week National Fuel Gas Company (NFG), which operates drilling subsidiary Seneca Resources and pipeline subsidiary Empire Pipeline, issued its fourth quarter 2018 (everyone else’s 3Q18) update. Via Seneca Resources, NFG drills wells in northcentral and northwestern PA. Via Empire Pipeline, they build and maintain hundreds of miles of pipelines in PA and New York, where the company is headquartered. NFG operates a utility (gas and electric) company in addition to Seneca and Empire. A lot of spinning plates to watch. But they do a great job. Much of the focus of the update was on the upstream–on Seneca Resources. According to CEO Ron Tanski, in 2019 more than half of the company’s capital expenditures will go for Seneca’s drilling program. Seneca has and will continue to operate three drilling rigs, with plans to expand production by 24%.
As we reported in March, Empire Pipeline, the midstream (pipeline) subsidiary of National Fuel Gas Company, filed an application with the Federal Energy Regulatory Commission (FERC) to build two new compressor stations along the Empire Pipeline–one in Tioga County, PA, the other in Ontario County, NY (see
Finally, a New York pipeline story with a happy ending. On Feb. 3, 2017, the Federal Energy Regulatory Commission (FERC) approved a long-delayed project–National Fuel Gas Company’s (NFG) Northern Access 2016 pipeline project (see 
Last week lawyers for National Fuel Gas Company and the New York Dept. of Environmental Conservation (DEC) were in federal court doing battle over the DEC’s arbitrary and capricious rejection of an important Marcellus pipeline project. Three years ago NFG proposed and filed to build the Northern Access Pipeline project–a $455 million project includes building 97 miles of new pipeline along a power line corridor from northwestern Pennsylvania up to Erie County, NY. The project also calls for 3 miles of new pipeline further up, in Niagara County, along with a new compressor station in the Town of Pendleton. The Federal Energy Regulatory Commission (FERC) granted final approval for the project in February of this year (see
Last week National Fuel Gas Company, headquartered in Western New York State with drilling subsidiary Seneca Resources and pipeline subsidiary Empire Pipeline, issued its fourth quarter (everyone else’s third quarter) 2017 update. In the accompanying analyst phone call, CEO Ronald Tanski blamed the delay of the Northern Access Pipeline project (delayed by the NY Dept. of Environmental Conservation) for lower earnings than the company would have otherwise realized. Thanks, business UNfriendly NY! You may recall in July NFG filed a lawsuit against the DEC for arbitrarily rejecting the project (see 
Yet more drama and intrigue in National Fuel Gas Company’s (NFG) lawsuit against the New York Dept. of Environmental Conservation (DEC). Three years ago NFG proposed and filed to build the Northern Access Pipeline project–a $455 million project includes building 97 miles of new pipeline along a power line corridor from northwestern Pennsylvania up to Erie County, NY. The project also calls for 3 miles of new pipeline further up, in Niagara County, along with a new compressor station in the Town of Pendleton. The Federal Energy Regulatory Commission (FERC) granted final approval for the project in February of this year (see
There’s been an interesting twist in the saga of National Fuel Gas Company’s (NFG) Northern Access Pipeline project. The $455 million project includes building 97 miles of new pipeline along a power line corridor from northwestern Pennsylvania up to Erie County, NY. The project also calls for 3 miles of new pipeline further up, in Niagara County, along with a new compressor station in the Town of Pendleton. The Federal Energy Regulatory Commission (FERC) granted final approval for the project in February of this year (see
Last week National Fuel Gas Company, headquartered in Western New York State with drilling subsidiary Seneca Resources and pipeline subsidiary Empire Pipeline, issued its third quarter (everyone else’s second quarter) 2017 update. NFG produced 567 million cubic feet per day (MMcf/d) of natural gas last quarter, a 6% increase over the same quarter a year ago. NFG realized an average price of $2.94 per thousand cubic feet (Mcf), up $0.08 per Mcf from the prior year. Compare that with Antero’s hedged average of $3.41/Mcf (see today’s story about Antero 2Q17). NFG CEO Ronald Tanski had some interesting remarks with respect to the company’s stalled Northern Access Pipeline project. As you may recall, the Andrew Cuomo New York Dept. of Environmental Conservation (DEC) is blocking Northern Access, like they blocked the Constitution Pipeline and a tiny spur project for the Millennium. Because NFG’s Northern Access project is stalled, they are shifting their budget and drilling further west, to do Utica drilling in locations where there is already pipeline infrastructure. So this is yet another case of the NY screwing up Marcellus drilling PA that would otherwise be happening. Landowners in PA can thank NY Gov. Cuomo for screwing them over. Tanski also mentioned the court case for Northern Access, and that FERC (Federal Energy Regulatory Commission) may step in and overrule the NY DEC, as is now being considered in the Constitution Pipeline case (see today’s lead story). Here’s the update from NFG…