MVP “Nutty” Protester Drops Back to Earth – Out of Food

The Nut has fallen to the ground–or more properly, gently helped to the ground by members of the U.S. Forest Service. On March 28 an off-her-rocker fossil fuel hater who refuses to give her real name, calling herself “Nutty,” climbed up a jury-rigged pole in the middle of a gravel road running through the Jefferson National Forest in Virginia. She’s trying to stop construction vehicles working on the Mountain Valley Pipeline (MVP) from using the road to access their legally-permitted construction sites. Her criminal act of lunacy recently inspired another woman to do the same thing (see “Nutty” is as Nutty Does – 2nd MVP Protester Goes Up a Pole in VA). The Forest Service cut off Nutty’s food and water supply back in April by blocking other nuts from passing her supplies. With no food, she decided it was time to come back to earth. After coming down, Nutty was taken to a hospital to be checked out, and given a citation to appear in court to defend her criminal acts. No doubt the “monopod” (pole with ropes to nearby trees) she occupied is already on the ground, cut up into little pieces…
Read More “MVP “Nutty” Protester Drops Back to Earth – Out of Food”


It was a big week for Sierra Clubbers. The radical environmental organization (that irrationally hates all fossil fuels, even fossil fuels they used to love, like natural gas) previously filed a lawsuit in the U.S. District Court of Appeals for D.C. asking the court to consider whether or not the Federal Energy Regulatory Commission (FERC) should have issued an approval for Mountain Valley Pipeline (MVP). MVP is a $3.5 billion, 301-mile pipeline that will run from Wetzel County, WV to the Transco Pipeline in Pittsylvania County, VA–to move Marcellus/Utica gas south. No, the court did not rule FERC was out of order in its decision. Not yet, anyway. This gets in the weeds just a bit, so bear with us. The first step in the process of challenging a pipeline is to ask FERC to rehear their decision. If FERC refuses to rehear (reconsider) the decision, then whoever asked for the rehearing is free to file a lawsuit in the court system to challenge FERC’s decision to approve a project. FERC has 30 days to make a rehearing decision–unless they pull out the “tolling order” card and play it. A tolling order allows FERC more time to decide on rehearing–months, even a year. FERC played the tolling order card here and told the court, “We haven’t decided on rehearing yet, so you need to toss out the radical Sierra Club lawsuit challenging our decision to approve MVP” (MDN condensed version). This week the court said a very loud “NO” to FERC’s request. The court further told FERC to get off its duff and make the rehearing decision within 30 days. In the meantime, the Sierra Club of course wants MVP construction “paused indefinitely” while they continue to tie it up in legal knots. Don’t look for that to happen…
Apparently the more bizarre your actions, the more likely you are to become a minor celebrity. That’s what’s happening for Grandma Red, Theresa “Red” Terry, who took the bizarre action of climbing a tree on her property and living in the top of it for a month–all in an attempt to stop the tree from being cut to make way for the Mountain Valley Pipeline (MVP). In the end Grandma Red came down when a judge told her she would begin paying $1,000/day for her bizarre behavior. Now that she’s back on terra firma, Grandma Red is meeting with state officials and attending radical Big Green rallies, showered with praise for her “courageous” action. What’s next? The Tonight Show and The Late Show? Meanwhile, in a well-timed and coordinated attack, Big Green lawyers are asking the 4th U.S. Circuit Court of Appeals to overturn the decisions of state and federal agencies to allow MVP, simply because Big Green doesn’t like the decisions. Big Green argued the court should overturn a decision by the Virginia State Water Control Board to allow MVP to build, crossing streams, and to overturn a decision by the U.S. Forest Service to allow MVP to build pipeline through a tiny sliver of Jefferson National Forest. Twenty years ago these lawsuits would have been laughed out of court because the country followed the rule of law. Today, with courts packed with Obamadroids, you just don’t know…
Despite all of the media attention on a handful of protesters who sit in the tops of trees or on top of a poll in order to block construction of the Mountain Valley Pipeline (MVP), the pipeline nonetheless continues to receive regular new permissions from the Federal Energy Regulatory Commission (FERC) to construct the actual pipeline and (yes), even to cut trees past the March 31 deadline. The good news is that MVP is on track to be completely built and flowing Marcellus/Utica gas by the end of THIS YEAR! Despite the best efforts of radical protesters and multiple lawsuits by Big Green groups. Recent FERC permissions for MVP include: (1) allow MVP to cut trees in Jefferson National Forest past the March 31 deadline; (2) build parts of the pipeline in Roanoke and Franklin Counties, VA; (3) work 24/7 on building a compressor station in Wetzel County, WV; and (4) build pipeline in Jefferson National Forest, on both the VA and WV sides…
Last September a group of 57 gentry landowners in Virginia and West Virginia, backed by an out-of-state Big Green group, sued the Federal Energy Regulatory Commission (FERC) in an attempt to gut the 80-year old Natural Gas Act that gives FERC the right to grant eminent domain for pipeline projects (see
Theresa “Red” Terry (whom we call Grandma Red) and her daughter Minor Terry finally came down from the trees where they were perched since April 2 in an illegal attempt to block Mountain Valley Pipeline (MVP) from cutting the trees. They came down on Saturday after a federal judge said if they stayed past midnight Saturday, they would each be fined $1,000 per day. The money would go to MVP. Red said, “Mountain Valley has taken enough from us…There wasn’t a lot more I could do up there besides show my ass and give them money.” As we previously reported, a number of Virginia lawmakers expressed their support of the Terrys and their flagrant disregard of the law (see
As EQT gets ready to split the company into two companies later this year, the midstream (pipeline & processing plants) portion of the company yesterday announced a complicated “drop down” deal to streamline the midstream operation. The short version is this: EQT has midstream assets spread throughout three companies on paper–EQT Midstream Partners, EQT GP Holdings, and Rice Midstream Partners. Yesterday the company announced all three are being merged under one umbrella–EQT Midstream Partners. As you’ll read in the EQT announcement, the entire deal is complex–with various entities buying assets from the others. One of the more interesting aspects of the deal is that EQT Midstream is buying EQT’s (the driller’s) Olympus Gathering System and EQT’s 75% interest in the Strike Force Gathering System. EQT Midstream is also buying out Gulfport Energy’s 25% interest in Strike Force, meaning EQT Midstream will now own 100% of Strike Force–a gathering pipeline system in the dry gas Utica covering 98,000 acres in Belmont and Monroe counties, in Ohio. Here’s the news that EQT is getting its midstream ducks in a row…
In October 2017, the Federal Energy Regulatory Commission (FERC) approved two important Marcellus/Utica pipeline projects–Dominion Energy’s Atlantic Coast Pipeline (ACP), and EQT Midstream’s Mountain Valley Pipeline (MVP) (see 
As Mountain Valley Pipeline (MVP) begins construction and launches a plan to expand their pipeline another 70 miles (see today’s lead story), the Virginia Dept. of Environmental Quality (DEQ) says it is eager to work with radical antis to monitor work that will be done by MVP in the Old Dominion. MVP is a $3.5 billion, 301-mile pipeline that will run from Wetzel County, WV to the Transco Pipeline in Pittsylvania County, VA–and perhaps beyond into North Carolina (see Mountain Valley Pipeline Launches Plan to Expand 70 Miles into NC). MVP is being built by EQT Midstream, NextEra Energy and several other partners. It has been hassled by protesters and sued by a cadre of Big Green groups–all with no result. The pipeline is currently under construction. Since there’s no stopping it, antis intend to launch a host of volunteer “monitors” to rat out pipeline workers that do anything from drop a candy wrapper on the ground to drive 2 miles an hour over a locally posted speed limit. In other words, a busybody brigade. To which we say: Go ahead–knock yourselves out. MVP has nothing to hide. If you want to waste your time, it’s yours to waste. The DEQ, under Democrat Gov. Ralph Northam, is only too happy to work with the busybody brigade to further hassle MVP…
Here’s the latest update in the ongoing story of “protesters” who are trying to stop progress in cutting trees for the Mountain Valley Pipeline (MVP), which will run from West Virginia into Virginia. We previously reported on illegal tree-sitters that judges and law enforcement refuse to remove (see
In January, MDN reported that Mountain Valley Pipeline (MVP)–a $3.5 billion, 301-mile pipeline that will run from Wetzel County, WV to the Transco Pipeline in Pittsylvania County, VA–had received permission from the Federal Energy Regulatory Commission (FERC) to begin tree clearing and construction of access roads and construction yards in five West Virginia counties (see
If the so-called “tree sitters” in Jefferson National Forest who are trying to block tree cutting for the Mountain Valley Pipeline (MVP) get themselves hurt, Monroe County Circuit Court Judge Robert Irons will be the one to blame. Well actually, the protesters can blame themselves (they’re idiots), but Irons is certainly complicit. On Tuesday Judge Irons refused to grant MVP a court order to remove the radical protesters. Apparently they are 7 feet outside of the right of way zone for tree felling. Have you ever cut a big tree down? Trees don’t care if they fall 7 feet this way or 7 feet that way when they fall. MVP wants to ensure the protesters don’t get hurt, and wants them gone before they cut trees near them. But because the radicals technically, according to the judge, are not in the actual right of way, they can stay up the trees where they’ve been for the past 25+ days. There are two suspended tree houses (platforms), held in the trees with ropes. Up to seven people have been living in the two magic tree houses, eating, breathing and defecating up in the trees (harming the environment they profess to be protecting). MVP technically has a deadline of March 31 to fell trees along the path of the pipeline. We suspect MVP has a Plan B for this segment where the loons have perched themselves up a tree. We predict sitting up a tree will get old sooner or later–and MVP can wait them out…