FERC Issues Compressor Permits for TGP’s East 300 Upgrade in NY, NJ
Tennessee Gas Pipeline’s (TGP) plan to flow more Marcellus gas to Westchester County, NY and New York City for Consolidated Edison customers, called the East 300 Upgrade Project, took a giant leap forward last Thursday when the Federal Energy Regulatory Commission (FERC) issued permits that allow TGP to upgrade two existing compressor stations (in PA), and build a brand new compressor station in West Milford (Passaic County, NJ), just across the border and not far from Westchester County. This is a major victory and a sign this project will now get completed.
Read More “FERC Issues Compressor Permits for TGP’s East 300 Upgrade in NY, NJ”


Tennessee Gas Pipeline’s (TGP) plan to flow more Marcellus gas to Westchester and New York City is called the East 300 Upgrade Project. The project involves upgrades at two existing compressor stations (in Pennsylvania), along with building a brand new compressor station in West Milford (Passaic County), just across the border and not far from Westchester County, NY. Radicalized fossil fuel haters at Food & Water Watch, one of the worst of the worst anti groups, is challenging the all-electric, no-emissions compressor station planned for Passaic County in New Jersey Supreme Court.
How many times must we say this before it sinks in: FERC (the Federal Energy Regulatory Commission) is an economic agency, NOT an environmental agency. FERC’s role is to ensure pipelines, electric transmission lines, etc. are able to get built and are economic and not an undue burden for ratepayers. FERC’s role is NOT to worry about so-called global warming. Yet the liberal Democrats inside FERC, and now the liberal Democrats on the U.S. Court of Appeals for the District of Columbia, insist FERC reopen already-approved projects, like a tiny pipeline expansion in Massachusetts, and re-do long-completed evaluations in light of global warming considerations. It’s INSANE.
Hackers, believed to be “state-sponsored,” aggressively targeted computers belonging to current and former employees at two dozen major natural gas suppliers and exporters. The aim seemed to be an attempt to cripple U.S. LNG exporting ability. One of the targets of the attacks was EQT Corporation, the largest natural gas producer in the U.S. The activity occurred on the eve of Russia’s invasion of Ukraine. You do the math to figure out who the “state sponsor” of the attacks was.
In December, Tennessee Gas Pipeline (TGP), a subsidiary of Kinder Morgan, filed a proposal with the Federal Energy Regulatory Commission (FERC) to implement a “responsibly sourced natural gas (RSG) supply aggregation pooling service” at select locations across the TGP system (see
Tennessee Gas Pipeline’s (TGP) plan to flow more Marcellus gas to Westchester and New York City is called the East 300 Upgrade Project. The project involves upgrades at two existing compressor stations (in Pennsylvania), along with building a brand new compressor station in West Milford (Passaic County), just across the border and not far from Westchester County, NY. For a second time this year, Passaic County commissioners have refused to vote in favor of a resolution opposing the project.
Over the past two years, MDN has told you about a tiny 2.1-mile looping pipeline segment proposed by Kinder Morgan’s Tennessee Gas Pipeline (TGP), to be buried next to the existing TGP, to connect regions around Springfield, Massachusetts to receive more natural gas supplies. Springfield neighborhoods like Holyoke have an ongoing moratorium on hooking up new natgas customers unless/until more supply is provided (see 

In an effort to flow more Marcellus natural gas to a gas-starved New York City, Kinder Morgan cut a deal with utility company Consolidated Edison in 2019 to beef up capacity along its Tennessee Gas Pipeline (TGP) that feeds NYC, allowing Con Ed to avoid cutting customers off from natgas hookups (see
In an effort to flow more Marcellus natural gas to a starving New York City, Kinder Morgan cut a deal with utility company Consolidated Edison in 2019 to provide more gas by beefing up capacity along its Tennessee Gas Pipeline (TGP) that feeds NYC, allowing Con Ed to avoid cutting customers off from natgas hookups (see 