Regulation

  • | | | |

    FERC Plays Hardball with Rover – Refuses to Certify 4 Laterals

    Rover Pipeline has violated one of the sacrosanct rules of life (and of pipeline construction): “Say what you’ll do, then do what you say.” Rover told the Federal Energy Regulatory Commission it would restore areas previously dug up to lay the pipeline by certain dates (primarily June 30th). In return, based on those promises from Rover, FERC allowed the company to begin service on certain sections of the $3.7 billion, 711-mile natural gas pipeline that runs from PA, WV and eastern OH through OH into Michigan and on to Canada via the Vector Pipeline. Rover has been pressuring FERC to allow two of the laterals–the Burgettstown and Majorsville laterals, that reach into western Pennsylvania–to begin service (see Rover Pressuring FERC to Approve Final 2 Laterals ASAP). We previously assumed (incorrectly) that the other six laterals were all online. That is not the case. Two more laterals are not yet online, in addition to the Burgettstown and Majorsville laterals. We’re not sure which ones. Laterals are offshoot pipelines that connect sources of gas to the main Rover pipeline–a critical component because you need the supply or you’ll have a partially empty mainline. In a letter dated last Thursday, FERC told Rover they haven’t lived up to their promises to restore areas they promised to restore by June 30th. The FERC letter (full copy below) says (1) Rover must provide a detailed list, chapter and verse, of why it has not lived up to its promises, and (2) informs Rover that until it does live up to its promises, they won’t be authorizing any more laterals to go online. FERC is playing hardball–far from the “industry rubber stamp” that antis attempt to portray FERC as…
    Read More “FERC Plays Hardball with Rover – Refuses to Certify 4 Laterals”

  • | | | | | |

    Mountain Valley Pipe Voluntarily Shuts Down Construction in Va.

    MDN told you last week that Sierra Club lawyers are attempting to bamboozle a court into halting construction of the Mountain Valley Pipeline (MVP) in Virginia, as they were able to do in West Virginia (see Enviro Radicals Target MVP in Va. Following WV Court “Win”). Turns out the enviro-nuts don’t have to worry–at least for now. Mother Nature has done it for them, has halted all construction of MVP in the Old Dominion. Following heavy rains that have resulted in erosion and runoff from the pathway along which the pipeline will be laid, MVP has voluntarily decided to, for the time being, halt all construction in Virginia. When will construction resume? According to an MVP spokesman: “There is no specific timeline for the suspension, however, as soon as upgrades are completed and approved by DEQ, construction can resume.” Let’s hope it’s sooner rather than later…
    Read More “Mountain Valley Pipe Voluntarily Shuts Down Construction in Va.”

  • | | | | | | |

    60-Mile Pipeline from NW PA to NE OH Gets Favorable FERC Review

    Click for larger version

    Last October MDN brought you details about the proposed $86 million Risberg Line pipeline project (see New 60-Mile Pipeline Proposed from NW Pa. to NE Ohio). The project will use approximately 32 miles of existing pipeline in an established Right of Way originating in the Meadville, PA area. Approximately 16 miles of new pipeline will be installed in Pennsylvania and approximately 12 miles of new pipeline will be installed in Ohio–meaning 28 miles of brand new “greenfield” pipeline needs to get built. Both the U.S. Army Corps of Engineers and the Pennsylvania Fish and Boat Commission are “cooperating agencies” and part of the environmental assessment (EA) review process, along with the lead agency, the Federal Energy Regulatory Commission (FERC). Good news: FERC issued the EA on Friday (full copy below), and the project passes with flying colors. While this is not a final stamp of approval (which is due by Sept. 27th), when FERC issues a favorable EA, it’s almost certain they will approve the project…
    Read More “60-Mile Pipeline from NW PA to NE OH Gets Favorable FERC Review”

  • | |

    Sad News: FERC’s Rob Powelson (from PA) Resigns Effective August

    FERC Commissioner Rob Powelson

    Robert Powelson, a Republican member of the Federal Energy Regulatory Commission (FERC) from the great state of Pennsylvania, appointed by President Trump, announced yesterday he is resigning effective in mid-August. He’s not even been in office a full year. This is devastatingly bad news in our book, for a couple of reasons. Coming from PA and previously serving on the state Public Utility Commission, Powelson has been a champion for natural gas and the pipelines that flow it–especially Marcellus/Utica projects. He’s been a superb FERC commissioner. So why is Powelson leaving? To become president and CEO of the National Association of Water Companies. No offense to that association (which we’d never heard of before), but this is a step down. The speculation whirling around is that Powelson is leaving FERC over differences of opinion with Team Trump and their ill-advised mission to prop up coal and nuclear energy, at the expense of natural gas. Apparently Powelson has had enough and wants out. It’s not only sad he’s leaving, it could be consequential in the near-term. Why? Because the Commission will be split 2-2 Republicans and Democrats, and the Dems have shown they’ve sold out to their radical elements, willing to vote against new pipeline projects in the name of man-made global warming, contrary to policy and stated regulation (see FERC Becomes Political as Seen in Rehearing Vote on NY Project). The politics in the Dem party is toxic and radical, and has now spread to FERC. Powelson’s departure at this time is not good news for our industry. We hope Trump can get a new FERC member appointed to replace Powelson asap–but don’t hold your breath. The swamp resists change at any cost…
    Read More “Sad News: FERC’s Rob Powelson (from PA) Resigns Effective August”

  • | | | |

    M-U Production May “Flounder” This Summer from Rover Pipe Delays

    Platts is reporting U.S. natural gas production hit a new, all-time high last week, mainly due to a surge in natgas production in the Texas Permian. Although Marcellus/Utica production “pulled back modestly” this past week, if you look at the entire month of June, we hit new all-time highs for production yet again. However, it wasn’t just the good news of new record production that caught our attention in the Platts update, but this statement: “Looking ahead, it’s possible that Northeast production growth could flounder this summer, thanks to continued in-service /delays on Rover Pipeline’s upstream supply laterals.” Rover is desperately trying to get FERC to grant permission to open the Majorsville and Burgettstown laterals, as we pointed out yesterday (see Rover Pressuring FERC to Approve Final 2 Laterals ASAP). So if those laterals were to go into service immediately, wouldn’t that mean production will spike up right away with no “floundering”? Not necessarily. Here’s why…
    Read More “M-U Production May “Flounder” This Summer from Rover Pipe Delays”

  • | | |

    Pipeline Cos. to D.C. – We Need Help to Beat Back Green Groups

    The World Gas Conference, held every three years in different locations around the globe, was held this week in Washington, D.C.–the first time back in the U.S. in 30 years. We’ve reported various stories from that event. Here’s another such story that caught our interest. Pipeline companies, specifically TransCanada and Enbridge (both based in Canada but with huge pipeline networks in the U.S.) told conference attendees that the pipeline industry needs help from Washington–from either the Federal Energy Regulatory Commission, or Congress, or both to fight back against the increasing efforts of Big Green groups opposed to fossil fuels. Fight back how? By adopting new regulations (FERC) or new laws (Congress) that favor pipeline infrastructure. Our interpretation of what they said: It’s time to stop allowing a small group of wacko radicals block energy progress in this country…
    Read More “Pipeline Cos. to D.C. – We Need Help to Beat Back Green Groups”

  • | | | | |

    Rick Perry Tells Cuomo – You’ll Face “Reckoning” for Blocking NatGas

    Yesterday, Dept. of Energy Secretary Rick Perry leveled a warning to Andrew Cuomo and the leaders of other states blocking natural gas pipelines: You will face a “real reckoning” of high energy costs and vulnerabilities (i.e. blackouts) because of your actions. Perry stopped short of saying Washington and the Trump Administration would use Executive Orders to unblock some of the blocked pipeline projects (which is a disappointment). But Perry alluded to that possibility when he said, “We have to have conversation as a country, is that a national security issue that outweighs the political concerns in Albany, N.Y.?” Cuomo should be concerned. We’re holding out hope that Trump will issue an Executive Order for both the Constitution Pipeline and Northern Access Pipeline projects, overruling Cuomo. It’s refreshing to see our side take the fight to the irrational radicals who oppose fossil fuel energy…
    Read More “Rick Perry Tells Cuomo – You’ll Face “Reckoning” for Blocking NatGas”

  • | | | | | | | |

    Rover Pressuring FERC to Approve Final 2 Laterals ASAP

    Click for larger version

    In a respectful, but strongly worded letter to the Federal Energy Regulatory Commission (FERC), Energy Transfer Partners’ Rover Pipeline asks FERC to (our words) get off its rear-end and approve the Burgettstown and Majorsville laterals. The two laterals, or off-shoots of the pipeline system, both reach into western Pennsylvania and are (from what we can tell) the final two pieces of the Rover pipeline that are not yet online. Rover asked FERC to approve the two laterals, along with other portions of the pipeline, by June 1st, in a letter dated May 24th. FERC did approve some items on the list, but not the two laterals (see M-U Gas Now Travels to Dawn Hub in Canada via Rover Pipeline). In a June 21 letter (read it below) Rover then asked FERC to approve the two laterals by June 25, this past Monday. That date came and went with no approvals. Rover said in its letter: “significant volumes of natural gas have been unable to flow on pipeline facilities that have been completed for nearly a month.” You can feel the frustration when reading the letter. So what, exactly, is the holdup anyway?…
    Read More “Rover Pressuring FERC to Approve Final 2 Laterals ASAP”

  • | | | | | | | |

    NY Asks FERC to Hassle AIM Pipeline, Restrict Flows

    Spectra Energy’s Algonquin Incremental Market (AIM) pipeline project is an $876 million expansion of the existing Algonquin pipeline system designed to carry 342 million cubic feet of natural gas per day to New England states that badly need the gas. On March 3, 2015 the Federal Energy Regulatory Commission (FERC) issued their final approval for the project, allowing it to go forward. Construction began in 2015 and, following extreme opposition from New York State over a small portion of the project, it finally went online in in 2016. New York’s radical, anti-drilling governor, Andy Cuomo, tried to stop the Algonquin using the flimsy excuse that some of the drilling for the pipeline would happen a half mile from a nuclear power plant–a plant that’s shutting down anyway (see Gov. Cuomo Asks FERC to Halt Algonquin Pipeline Near Nuke Plant). A few weeks after Cuomo requested FERC shut it down, they told him “no”–which was the cue for Big Green groups to file an appeal with the liberal District of Columbia Court of Appeals (see Radical Enviro Groups File Appeal to Stop AIM Pipeline in NY/CT). Didn’t work. New York State’s two radically leftist Democrat Senators, Chuck Schumer and Kirsten Gillibrand, the Senator nobody knows about and nobody cares about, tried to stop it too (see NY’s 2 Radical Senators Call for Halt in Building Algonquin Pipeline). Didn’t work. Now that the pipeline expansion has been up and running safely for more than a year, you’d think they would give up. Nope. Cuomo previously ordered a “safety analysis” of the project, back in 2016. That report was just released (executive summary embedded below) and four state agencies, all under the executive branch umbrella (i.e., under Cuomo’s thumb), jointly wrote a letter to FERC asking FERC to further hassle the AIM project by restricting flows along it and shutting it down when work to decommission the nearby nuke plant begins…
    Read More “NY Asks FERC to Hassle AIM Pipeline, Restrict Flows”

  • | | | | | | | | |

    PA DEP Notifies Shell of “Technical Deficiencies” with Ethane Pipe

    Shell delivered some good news at last week’s Northeast U.S. Petrochemical conference in Pittsburgh: The Falcon ethane pipeline will get built next year (see Shell Says Falcon Ethane Pipeline to Get Built in 2019). The pipeline won’t actually flow ethane to the Shell cracker in Monaca until 2020 at the earliest, because the cracker plant itself won’t go online until 2020 at the earliest. The 97-mile consists of “two legs,” with about half of the pipeline located in PA, the other half in OH. The Pennsylvania Dept. of Environmental Protection (DEP) conducted three public hearings on the project earlier this year, in preparation for issuing permits. Antis came out in force and behaved badly, as they typically do (see More of the Same at Final DEP Hearing for Shell Ethane Pipeline). No matter. The pipeline will get built. But not without jumping some hurdles first. On June 1, the DEP issued three letters identifying what it calls “serious technical deficiencies” in Shell’s pipeline plan, for townships in three different counties along the pipeline’s PA route. Shell maintains this type of notification is “common” in the permitting process, and is committed to working with the DEP to address any issues of concern…
    Read More “PA DEP Notifies Shell of “Technical Deficiencies” with Ethane Pipe”

  • | |

    Indiana Utility Files Request to Build New Gas-Fired Electric Plant

    Many (most?) electric generating companies in the U.S. are regulated–highly regulated. They’re guaranteed a certain, predictable level of (low) profits. But in return for guaranteed profitability, every single thing they do is monitored and authorized in triplicate, with one or another government agency reviewing anything and everything that happens. It’s the deal they’ve struck with the regulatory devil. Vectren is one such regulated utility in the great state of Indiana. Vectren operates the F. B. Culley Generating Station, a 369 megawatt (MW) coal power plant located in Warrick County, Indiana. They plan to close the coal-fired plant in 2023. In its place, they want to build a 900 MW natgas-fired plant and a 50-acre solar farm. Building the gas plant and solar farm would cost Vectren (meaning ratepayers) $940 million. The cost is passed on to ratepayers because Vectren is regulated. That’s the way it works. The bargain struck with the devil. The gas-fired plant will be cleaner than coal, more efficient, cheaper to operate, and better for the environment. We suspect Utica/Marcellus gas would help feed the plant. And yet, anti-fossil fuel wackos oppose the plan to switch to cleaner-burning natgas. Would they prefer no electricity?…
    Read More “Indiana Utility Files Request to Build New Gas-Fired Electric Plant”

  • | | | | |

    SRBC Elects New Officers, NY Becomes Chair on July 1

    Perhaps the proposed legislation by PA Rep. Dan Moul (Republican from Gettysburg) to gut not only the DRBC (Delaware River Basin Commission) of its power to regulate groundwater, but also to gut the SRBC (Susquehanna River Basin Commission), is not so far off the mark after all (see PA House Bill to Neuter SRBC, DRBC Makes It to First Base). We always viewed the SRBC as a good steward of water resources within the river basin it governs, preferring to “stay in its lane” and not presume to regulate shale drilling the way the DRBC has (see SRBC Tells Anti-Drillers “We’ll Stay in Our Lane” on Water Study). Apparently each year (or two or three, we’re not sure) the SRBC rotates the positions of Chair and Vice Chair among its four members (US Army Corps of Engineers, New York, Pennsylvania, Maryland). Currently the Chair belongs to the Army Corps, but on July 1st it will change to NY. The problem is that NY’s rep on the Commission is Basil Seggos, NY Dept. of Environmental Conservation (DEC) Commissioner and an appointee by Andrew Cuomo. Seggos is a hardened, very politically left anti-fossil fueler–a puppet and tool of Cuomo. Will this change in leadership at the SRBC have an impact on how the organization operates?…
    Read More “SRBC Elects New Officers, NY Becomes Chair on July 1”

  • | | | | | |

    Constitution Pipe Asks FERC for Speedy Rehearing, 2020 Deadline

    Seems like a week doesn’t go by that MDN isn’t asked (by someone from Pennsylvania), “Is there any hope of building the Constitution Pipeline through New York?” Our standard response is this: The only way it gets built is (a) NY elects a new governor favorable to the industry–about a 1% chance of that happening, (b) President Trump issues an Executive Order overriding Cuomo’s blockade of Constitution (and other pipeline projects)–maybe a 10% chance of that happening, or (c) the Federal Energy Regulatory Commission (FERC) reconsiders a decision to not overrule NY’s move to block the project–maybe a 15% chance. The U.S. Supreme Court in April refused to consider the Constitution Pipeline case, closing that door (see Supreme Court Rejects Constitution Pipe Request to Overrule NY). In January of this year, FERC turned down Constitution’s request to overrule NY (see Death of the Constitution Pipeline? FERC Refuses to Overrule NY DEC). But then Constitution (i.e. Williams) asked FERC to reconsider their ruling, to “rehear” the case as it’s called, in Feburary (see Constitution Pipe Files for FERC Rehearing, Then Back to Court). In March, FERC gave themselves a little more time to think about rehearing the decision, but since that time, the agency has been silent. Yesterday Williams/Constitution filed a request with FERC asking them to urgently, speedily, quick-like-a-bunny, pretty-please with a cherry on top hurry up and reconsider/rehear their earlier decision, this time hopefully overruling NY. Could it happen? Sure, it could. Will it? Doubtful, but hey, hope springs eternal! Williams/Constitution also filed an official request yesterday with FERC to extend the deadline to build the Constitution project–from this year to 2020. If FERC grants the extension, then maybe there is a glimmer of hope that FERC will change its mind, or that FERC somehow sees a way that Constitution can still get built…
    Read More “Constitution Pipe Asks FERC for Speedy Rehearing, 2020 Deadline”

  • | | | |

    Ohio Approves $900M Harrison County Power Plant in Cadiz, OH

    Click for larger version

    In September 2016, MDN reported that EmberClear planned to fund and build a new $900 million, 1,000-megawatt electric generating plant in Harrison County, OH (see $900M Utica Gas-Fired Electric Plant Coming to Harrison County, OH). The new plant will be fed by Utica Shale gas. EmberClear was, until July 2016, a Canadian-based company. But it went bankrupt and after emerging from bankruptcy it changed its name to Ember Partners, now based in Houston, TX. Since 2016 we haven’t heard anything about the project. But things were/are happening. Last week the Ohio Power Siting Board (OPSB) authorized construction of the 1,050 megawatt (MW) natural gas-fired, combined-cycle electric generation facility in Cadiz–called the Harrison Power Plant. Which is good news indeed. The plant will generate 500 temporary construction jobs and 30 permanent jobs and use a huge amount of natural gas to power it (good for Utica drillers!). Construction on the plant is due to begin in October of this year and the plant will be done and online in June 2021. Here’s the details…
    Read More “Ohio Approves $900M Harrison County Power Plant in Cadiz, OH”

  • | |

    Rhode Island Gas-Fired Plant Making Money – Before It’s Built!

    At a big ceremony in 2015, none other than Rhode Island Gov. Gina Raimondo joined the CEO of Invenergy to announce the Clear River Energy Center–a 900-1,000 megawatt electric generating plant that runs on natural gas (see New NatGas Powered Electric Plant Coming to…Rhode Island?!). A new gas-fired plant planned for the socialist paradise of Rhode Island, home to old money and people who oppose change of any kind. Who woulda thunk? The new plant will lower RI residents’ electric bills by a collective $280 million and replace aging coal and oil power plants–cleaning the air in the process. With the jobs created, the investment in the facility, and lower electric rates, it’s calculated this single plant will have a $1.3 billion impact on the economy of RI. The plan was to begin construction in summer 2016 and have the plant up and running by 2019. What’s happened since the initial announcement? A lot of bureaucratic bull. The project is under review now and a final decision by the Rhode Island Public Utilities Commission will not happen until January of next year. In the meantime, the plant is making money, even though it’s not yet built! How? By selling its contracts to provide electricity. The plant won’t be running next year, so Invenergy, the builder, has sold the right to provide electricity to the grid (for a time) to different plant…
    Read More “Rhode Island Gas-Fired Plant Making Money – Before It’s Built!”

  • | | | |

    SWPA Gas-fired Elec Plant Next to Pot Farm Nears Final Approval

    Last October MDN told you that a second Marcellus gas-fired electric generating plant is planned for Greene County, PA (see 2nd Marcellus-Fired Electric Plant Proposed for Greene County, PA). Hill Top Energy Center, based in Huntington Bay, N.Y., is planning to build a 620 megawatt plant on 41 acres of land off Thomas Road in Cumberland Township. The PA Dept. of Environmental Protection (DEP) held a public hearing in early November, and in early December the DEP issued an air quality permit for the project (see PA DEP Issues Air Permit for Gas-fired Elec Plant Next to Pot Farm). The plant will be built next door to a “medical marijuana operation”–i.e., a pot growing farm. Here’s an idea: Why not burn pot to generate the electricity instead of natgas? Roughly the same CO2 footprint, with the added benefit of lacing the air in the region with happy smoke. Oh well, back to reality. What’s left to do before construction begins on the Hill Top Energy Center? The facility needs a building permit from Cumberland Township. Plans will be reviewed at the next town meeting on July 2. If the plans are approved, a building permit will follow in short order. However, Hill Top says they don’t plan to begin construction until early 2019…
    Read More “SWPA Gas-fired Elec Plant Next to Pot Farm Nears Final Approval”