Marcellus/Utica Region Could Support 4 More Crackers, but Will It?
In March of this year, the Team Pennsylvania Foundation released a report called “Prospects to Enhance Pennsylvania’s Opportunities in Petrochemical Manufacturing” (see PA Study Finds Marcellus/Utica Can Support 4 More Ethane Crackers). The report is derived from a comprehensive study conducted by powerhouse oil & gas consulting firm IHS Markit. According to the report, Pennsylvania can easily handle another two ethane cracker plants (aside from the already under construction Shell cracker), and Ohio and West Virginia can handle another two cracker plants between them, for a total regional capacity of another four ethane cracker plants. But realistically, will another four actually get built in our region? That was the topic addressed during the Northeast U.S. Petrochemical Construction conference held earlier this week in Pittsburgh. PA officials talked openly and honestly about the challenges in attracting more crackers–and about their mission, which is “the development of sites” to attract more crackers. It was an interesting, and candid, discussion with helpful information about what crackers look for in a potential site…
Read More “Marcellus/Utica Region Could Support 4 More Crackers, but Will It?”


In reading a fascinating story about European chemical plant giant Ineos, the article took an unexpected turn when it said Ineos, indeed all of Europe’s petrochemical industry, is “vulnerable as never before because of the shale oil and gas boom in the US, which has made energy costs there just a fraction of those in Europe.” The article specifically names and credits the Marcellus with producing feedstock that is far cheaper than can be found in Europe–and chemical plants are now choosing to relocate and manufacture their products in the U.S. rather than Europe. The inescapable conclusion: if the United Kingdom (and Europe) refuses to frack, they’re hosed. Ineos, which has figured this out, has “quietly” purchased “some interesting onshore fracking licences” in the UK, and they intend to use them…
Believe it or not, Shell previously hired a third-party consultant to perform a traffic study in the area where Shell plans to build a $6 billion ethane cracker in Beaver County, PA. Based on the findings and recommendations of that study, Shell has begun to secure parking spots for construction workers that will descend on that location to build the plant–beginning later this year. One of the recommendations is to limit the number of parking spots to no more than 1,500 at any one location. Shell currently has three locations lined up and (mostly) ready to go, enough for 3,100 parking spots. At its peak, the project will employ something like 6,000 workers. So either Shell will line up more spots, or maybe workers will carpool…
An economic report released yesterday by the American Chemistry Council (ACC) shows that the Appalachian region could become a second center of U.S. petrochemical and plastic resin manufacturing, similar to the Gulf Coast. ACC President and CEO Cal Dooley presented the findings at a Capitol Hill press event with lawmakers including Senator Shelley Moore Capito (R-W.Va.), Senator Joe Manchin (D-W.Va.) and Rep. David McKinley (R-W.Va.). “The Appalachian region has distinct benefits that could make it a major petrochemical and plastic resin-producing zone,” Dooley said. “Proximity to a world-class supply of raw materials from the Marcellus/Utica and Rogersville shale formations and to the manufacturing markets of the Midwest and East Coast has already led several companies to announce investment projects, and there is potential for a great deal more.” What will it take to turn our region into another Gulf Coast petchem powerhouse? According to the report, an NGL (natural gas liquids, i.e. ethane) storage hub. You may recall Sens. Capito and Manchin recently introduced a bill to study an Appalachian NGL storage hub (see
As we have endlessly covered, Shell is in the midst of building a $6 billion ethane cracker plant in Beaver County, PA (see
Whenever a big, important project like the Shell ethane cracker, reported to be a $6 billion investment, goes forward, a whole lotta people were involved before the decision was made. However, if there is one universal truth in business it is this: There is always a champion at the center of any important project. The one person who’s responsibility it is to propel that project forward. The person who, we like to say, has their “butt in a sling.” It is on their shoulders to ensure the projects success. When you dig down into the story of the multi-billion dollar Shell cracker plant now being built in Beaver County, PA, you will find that one person. His name is Brent Vernon. He worked for more than five years to lure Shell to the Keystone State. Vernon was senior project manager for energy for the state when he began working, full time, on the Shell project in 2011. Since then he was promoted, first to deputy director and eventually director of the Governor’s Action Team, a role he continues. Vernon is key–one of the linchpins without whom the Shell deal would not have happened…

Positive economic signs continue to pop up with respect to Shell’s multi-billion dollar ethane cracker project in Beaver County, PA. Here’s the latest major economic impact from the project. A local developer has filed for a state grant to build a massive new housing project 2.5 miles from the cracker site. The new project calls for 450 housing units, retail space, a golf course, swimming pool and parking garage. What’s that? What happens after the cracker is built and the “temporary” workers, who would be living in this new complex for the next 5-10 years, leave? Great question! Answer: Turn it into a retirement community…
Back in January MDN reported that Denise Brinley, a special assistant to the Secretary of the state Department of Community and Economic Development, spilled the beans on an upcoming report PA had commissioned. Brinley said the report would be released “in the coming weeks” and it would show that Pennsylvania can easily handle another two ethane cracker plants (aside from the already under construction Shell cracker), and that Ohio or West Virginia could also handle another two cracker plants (see
Some 400 business, education and government officials attended a sold-out forum last week in Titusville, PA to hear about doing business with the $6 billion Shell ethane cracker project in Beaver County, PA. The stakes are high. One PA official said, “This is the greatest generational economic development we’ve seen in Pennsylvania, maybe ever.” According to a Louisiana resident involved with crackers in his state, for ever job the Shell cracker creates there will be 8.3 jobs somewhere else–at other companies in the region–to support the plant. It is an incredible opportunity. The question, for businesses in the region, is: How do we get a piece of the cracker pie? We now have an answer–at least in part. If you want to supply goods and services for the construction of the plant, the key is in working with the main contractor building the plant–Bechtel. Below we have details on how to plug in to the Bechtel supply chain system, along with advice for job seekers who want to work at the cracker plant once it’s built…
Jim Sewell, the Environmental Manager for the Shell ethane cracker project being built in Beaver County, PA, recently gave an update on the project to members of the Ohio Valley Oil and Gas Association. Sewell spoke about the reason Shell chose the Monaca site. He also gave an update on progress at the site. The biggest problem they’re trying to solve right now? Parking for workers…