Pipelines

  • | | | | | |

    Ohio EPA Grants Water Permit to NEXUS Pipe, “Learned” from Rover

    At a staged media event yesterday, Ohio EPA director Craig Butler had no end of insults for Energy Transfer and their Rover Pipeline project, making wild claims that the company now owes the state $2.3 million in fines (see today’s companion story). However, at the same media event, Butler had faint praise for another project–NEXUS Pipeline. The OEPA issued a federal water permit for the project on Tuesday. NEXUS is a $2 billion, 255-mile interstate pipeline that will run from Ohio through Michigan and eventually to the Dawn Hub in Ontario, Canada. The project is co-owned by DTE Energy of Detroit and Spectra Energy (now part of Canadian company Enbridge). NEXUS got final approval from the Federal Energy Regulatory Commission in August, the first major pipeline to get approved following a newly restored quorum at FERC (see New FERC Quorum Votes Final Approval for NEXUS Pipeline). At yesterday’s media circus, Butler said he and his agency have learned from their “mistakes” with Rover, and that NEXUS’ application includes much more detailed plans. Although OEPA likes the NEXUS paperwork, the agency is requiring more “contingency and storm water planning” from NEXUS as a condition of the permit…
    Read More “Ohio EPA Grants Water Permit to NEXUS Pipe, “Learned” from Rover”

  • | | | |

    PennEast Pipe Files Water Permit Request with USACE, Antis Erupt

    Click map for larger version

    Last week PennEast Pipeline, a $1 billion, 118-mile pipeline from Luzerne County, PA to Mercer County, NJ, filed a request with the U.S. Army Corps of Engineers for water crossing permits (full copy below). PennEast has faced a series of legal challenges–in particular from virulent Big Green groups THE Delaware Riverkeeper (Maya van Rossum) and the New Jersey Sierra Club (Jeff Tittel). Somehow Big Green groups seem to have been able to exert undue influence over the New Jersey Dept. of Environmental Protection, which rejected granting water permits in June (see NJ DEP Rejects Water Permit for PennEast Pipeline – What’s Next?). However, PennEast continues to make progress. In April the Federal Energy Regulatory Commission (FERC) issued a favorable, final environmental impact statement for the project, which is typically a prelude to issuing a final go-ahead (see FERC Issues Favorable Final EIS for PennEast Pipeline Project). Earlier this year, in February, the Pennsylvania Dept. of Environmental Protection issued a water permit for the project, which is being challenged in court by Big Green groups (see PennEast Pipeline Gets 401 Water Quality Certificate from PA DEP). PennEast acknowledges the Army Corps will still need information from other government agencies before it grants a water permit–but that’s OK. PennEast is simply getting its ducks in row by filing now, which has antis like van Rossum and Tittel in a dither…
    Read More “PennEast Pipe Files Water Permit Request with USACE, Antis Erupt”

  • | | | | | | |

    Rich Homeowners in Philly Suburb Claim ME2 Work Stirring up Arsenic

    Rich, snobbish homeowners in an “upscale” Philadelphia suburb development are asking an appeals court to stop Sunoco Logistics from building the Mariner East 2 pipeline through the edge of their high-priced development because, they claim, the digging is disturbing the dirt (which is what digging does) and disturbing the dirt is causing lead and arsenic to become dislodged. The lead and arsenic are supposedly in the dirt as a result of pesticides used when the land was an apple orchard. The claim is flat out BS–Barbara Streisand. The Andover Homeowners Association in Thornbury Township (Delaware County) is the same group that a few weeks ago acted like five year-olds by intentionally stepping over a painted line put there to protect them from a ME2 construction zone (see Philly Antis Step Over the Line (Literally) at ME2 Pipeline Site). Spoiled rotten children grow up to be spoiled rotten adults. Here’s the latest tactic to stop a pipeline from the gentry class–just because they don’t like how digging a pipeline makes their development look to the neighbors…
    Read More “Rich Homeowners in Philly Suburb Claim ME2 Work Stirring up Arsenic”

  • | |

    3 Pipelines About to Change Marcellus/Utica, Spur More Drilling

    Every now and again it’s helpful to step back and look at the big picture, in particular with respect to major pipeline projects. These projects have a deep and profound effect on drilling. In fact, the addition of just three pipelines in our region (currently under construction) will fundamentally change the price of gas in the Marcellus/Utica region–and ultimately lead to more drilling. How so? As part of an article on the Seeking Alpha investor’s website, author and investor Callum Turcan wrote about “Why Appalachia Matters” in which he details that three pipeline projects already getting built will provide an extra 6.45 billion cubic feet per day (Bcf/d) of capacity to flow our natural gas out of this region to other regions. Some of that capacity is already happening, with a partial startup of Rover Pipeline. When Rover is completed in early 2018, it will flow 3.25 Bcf/d of natural gas out of our region. Massive! In addition, Atlantic Sunrise is now under construction and when it is completed by the middle of 2018, it will flow 1.7 Bcf/d of gas out of the area. Finally, Leach XPress is due to be done by the end of THIS YEAR, and when it is, it will flow an extra 1.5 Bcf/d of gas out of the area. What will be the response? It’s pretty easy to predict that (a) prices for our gas will go up, and when prices go up, (b) drillers will complete wells already drilled but not yet completed (DUCs), and then (c) begin to drill more new wells. Those three pipelines aren’t the only ones that will get built…
    Read More “3 Pipelines About to Change Marcellus/Utica, Spur More Drilling”

  • | | | | | |

    Atlantic Sunrise Gets Ready to Cross 5 Towns in Lebanon County, PA

    As MDN reported yesterday, construction work on two compressor stations part of the Williams $3 billion Atlantic Sunrise Pipeline project began last Friday, the same day the Federal Energy Regulatory Commission (FERC) gave the project permission to begin construction (see Williams Breaks Ground on Atlantic Sunrise Pipe, Ahead of Schedule). Next up will be digging to lay the pipeline itself. The Lebanon Daily News reports residents in Lebanon County can count on seeing activity there “any day now.” The article names the five townships where the pipeline will cross, and says first up will be staging of equipment, then tree clearing, and finally (perhaps in mid-to-late October) the pipeline itself will get laid in the ground. A few antis in Lebanon have been quite vocal against the project over the past couple of years (see Lebanon County Antis Want Public (Spectacle) Mtg or No Mtg at All). Interestingly, over the past year or so Lebanon antis have been mum. Will we see any nutjobs chain themselves to bulldozers in Lebanon County? We doubt it, but you never know. Depends on whether or not out-of-town Big Green groups send troublemakers into the area. Here’s the list of five towns fortunate enough to see the Atlantic Sunrise, along with the list of four contractors hired to build the pipeline…
    Read More “Atlantic Sunrise Gets Ready to Cross 5 Towns in Lebanon County, PA”

  • | | |

    Rover Pipeline: Growing the Pie, or Stealing Slices from Others?

    Rover Pipeline–$3.7 billion, 711-mile natural gas pipeline that will run from PA, WV and eastern OH through OH into Michigan and eventually into Canada–starting flowing natural gas through a portion of the pipeline on Sept. 1st (see Big Portion of Rover Pipeline Now Up & Running – Thru Most of Ohio). Since then, Phase 1A of the pipeline has steadily increased its throughput and now flows over 700 million cubic feet per day (MMcf/d) of yummy Utica/Marcellus Shale gas to Defiance, OH. But where does that gas come from? Have a bunch of drillers suddenly flipped a switch and turned on new wells to fill that capacity? Well, to some degree that has happened. There is certainly new gas finding its way through Rover–but most of the gas flowing through Rover comes at the expense of flowing through other pipelines. Several other pipelines in the region are giving up some of their gas according to the experts at BTU Analytics. Which pipelines? Most of the gas flowing through Rover likely comes from gas that would have flowed through the Texas Eastern Transmission Company (TETCO) pipeline, says BTU Analytics. In addition, REX (Rockies Express Pipeline) and Dominion Pipeline have also lost some business to Rover. Here’s how Rover has changed the supply/demand landscape over the past three weeks…
    Read More “Rover Pipeline: Growing the Pie, or Stealing Slices from Others?”

  • | |

    Congress Needs to Fix State Vetoes of Federal Pipeline Projects

    As we have reported, history was made last Friday when the Federal Energy Regulatory Commission (FERC) overruled the New York Dept. of Environmental Conservation’s (DEC) denial of a water permit for Millennium Pipeline’s tiny 7.8 mile pipeline spur from the main Millennium Pipeline to a natural gas power plant under construction in Orange County, NY (see History Made! FERC Overrules NY DEC on Millennium Pipe Permit). The DEC eventually denied the water permit, but not before taking 19 months to do it. According to federal law, states have a maximum 12 months in which to make a federal Clean Water Act water permit decision. FERC said NY took too long, and therefore waived the permit, allowing Millennium to proceed with construction of the pipeline. The federal law governing all of this was written to give states a voice, but not a veto, of federal pipeline projects. Whether or not a project gets built is NOT up to the individual states–it is up to FERC and (if necessary) the U.S. Court of Appeals. The law specifically foresaw one state denying a project that another state needs and wants. However, rogue states like socialist NY are pushing the bounds of law by denying pipeline projects authorized by FERC. So what if NY rejects a pipeline, denying a water permit, but does so within the 12 month time period? What then? The legal beagles at the Blank Rome law firm address that issue on their environmental blog. Mike Krancer (former PA DEP Secretary), Fred Lowther and Margaret Anne Hill write that it’s time for Congress to act to clarify the law and ensure NY (and other states) cannot block federally approved pipeline projects…
    Read More “Congress Needs to Fix State Vetoes of Federal Pipeline Projects”

  • | | | | | | | |

    Williams Breaks Ground on Atlantic Sunrise Pipe, Ahead of Schedule

    Earth moving has begun for a compressor station in Columbia County. (Williams Partners)

    Well that didn’t take long! Yesterday MDN brought you the fantastic news that the Federal Energy Regulatory Commission (FERC) had granted Williams a certificate/go-ahead to begin construction on Atlantic Sunrise, a $3 billion, 198-mile natural gas pipeline project running through 10 Pennsylvania counties to connect Marcellus Shale natural gas from northeastern PA with the Williams’ Transco pipeline in southern Lancaster County (see FERC Greenlights Construction of Atlantic Sunrise Pipeline). FERC issued their permission to begin construction last Friday. Based on a previous Williams statement, we expected construction to begin tomorrow, on Sept. 20th. However, as soon as Williams had the certificate in their hands, they began construction–LAST FRIDAY. Where? Williams fired up bulldozers at two locations–one in Wyoming County, the other in Columbia County (both in northeast PA), to clear land for two new compressor stations they will build as part of the project. Yesterday both Williams AND Cabot Oil & Gas issued the same press release to announce construction has begun. Interesting that Cabot issued the release too, showing just how important this project is to Cabot’s future (and to their stock price)…
    Read More “Williams Breaks Ground on Atlantic Sunrise Pipe, Ahead of Schedule”

  • | | | | | |

    FERC Lifts Rover Horizontal Drilling Ban, Pipeline Work Resumes

    Rover Pipeline–$3.7 billion, 711-mile natural gas pipeline that (will eventually) run from PA, WV and eastern OH through OH into Michigan and on to Canada–began flowing natural gas through a large portion of the pipeline on Sept. 1st (see Big Portion of Rover Pipeline Now Up & Running – Thru Most of Ohio). In the past three weeks, Phase 1A of the pipeline has steadily increased its throughput and now flows over 700 million cubic feet per day (MMcf/d) of yummy Utica/Marcellus Shale gas to Defiance, OH. However, it could flow more, if the Federal Energy Regulatory Commission (FERC) would lift its considerable boot off Rover’s neck and let them finish Phase 1B pipeline work in eastern Ohio to feed more gas to the main part of the pipeline. The problem is that Rover had early missteps, the most serious of which spilled 2 million gallons of non-toxic drilling mud in a swamp near the Tuscarawas River back in April (see Rover Pipeline Accident Spills ~2M Gal. Drilling Mud in OH Swamp). An investigation by the Ohio Environmental Protection Agency (OEPA) found the presence of diesel fuel in the drilling mud, which means the mud wasn’t so non-toxic after all (see OH EPA Says Diesel Fuel Found in Rover 2M Gal Drilling Mud Spill). Rover believes sabotage may have been the cause. Since April, FERC has blocked all new underground HDD work for the Rover project. Rover has asked (begged, pleaded) FERC, several times, for permission to restart the HDD work–at least in a few select locations. In August, FERC issued eight conditions before they would agree to lifting the HDD ban (see FERC Issues Rover 8 Commandments to Restart Horizontal Drilling). Rover says they have met all of those conditions. However, the OEPA says they have not. Last week OEPA asked FERC to continue blocking HDD activity until they (OEPA) are satisfied (see Rover Pipeline Still Battling Ohio EPA, Asks FERC to Lift HDD Ban). Rover fired off a letter to FERC that says OEPA’s public statements are opposite of their private statements with Rover. In other words, OEPA is lying. Who will FERC listen to? Now we know. They’re listening to Rover. Yesterday FERC lifted the ban on HDD for nine key locations–NOT including the Tuscarawas River site. FERC says they are still investigating that spill. FERC said, in lifting the HDD ban, that “Rover has demonstrated sufficient progress on the required rehabilitation and restoration of the areas affected by the inadvertent release and drilling mud contamination” and that the company is following FERC’s 8 Commandments. We’re pretty sure yesterday’s FERC decision won’t make the OEPA happy…
    Read More “FERC Lifts Rover Horizontal Drilling Ban, Pipeline Work Resumes”

  • | | | | | | |

    Constitution, NFG Pipes to Seek FERC Relief from NY DEC Tyranny

    Yesterday we told that you history has been made–the Federal Energy Regulatory Commission (FERC) has broken the back of the New York Dept. of Environmental Conservation (DEC) by overturning the DEC’s decision to block a short pipeline Millennium wants to build to a power plant in Orange County (see History Made! FERC Overrules NY DEC on Millennium Pipe Permit). The DEC has also blocked federally-approved pipeline projects in two other cases–the Constitution Pipeline, a $683 million, 124-mile pipeline from Susquehanna County, PA to Schoharie County, NY carrying Marcellus gas (a Williams project), and the Northern Access Pipeline, a $455 million project includes building 97 miles of new pipeline along a power line corridor from northwestern Pennsylvania up to Erie County, NY, to carry Marcellus gas northward (a National Fuel Gas Company project). Given Millennium’s success in having FERC overrule NY DEC, one would think these other two projects would also file requests with FERC for the same thing. According to Reuters, NFG already has filed such a request, and Williams is about to…
    Read More “Constitution, NFG Pipes to Seek FERC Relief from NY DEC Tyranny”

  • | | | |

    Sierra Club Radicals Use FL Court Case to Challenge 2 M-U Pipelines

    In August, the D.C. Court of Appeals ruled in a case that may have long-term, very negative consequences for the oil and gas industry related to pipeline development (see DC Court of Appeals Legislates New Law re FERC & Global Warming). The profoundly litigious, anti-fossil fuel radicals of the Sierra Club previously filed a lawsuit against the Federal Energy Regulatory Commission (FERC) blaming FERC for not considering mythical man-made global warming as it conducted a review of three pipelines in the southeast. The Sierra Club is known for filing frivolous lawsuit after frivolous lawsuit. This is just one in a long line. The Southeast Market Pipelines Project is an umbrella project for three natural gas pipelines in Alabama, Georgia, and Florida. The linchpin of the project is the Sabal Trail pipeline, which travels from Tallapoosa County in eastern Alabama, across southwestern Georgia, and down to Osceola County, Florida, just south of Orlando (nearly 500 miles), feeding gas-fired power plants in the region. The Sierra Club antis said the three projects together didn’t take into consideration an increase in carbon and methane that would result from the three projects getting approved, and that said carbon and methane will contribute to man-made global warming. The D.C. Court of Appeals agreed and instructed FERC to reconsider its environmental assessment of the three projects–vacating an approval of the main part of the project, the Sabal Trail pipeline. Just one teeny tiny problem (for the antis): all three pipelines–Sabal Trail, Hillabee Expansion and Florida Southeast Connection–are up and running. This decision likely will not shut them down. But the decision does have a big impact on projects not yet built. Drunk on their earlier success, yesterday the Sierra Club filed two requests (demands?) with FERC requesting the agency redo their already-done environmental impact statements for Dominion’s $5 billion Atlantic Coast Pipeline from WV through VA and into NC, and for EQT’s $3.5 billion Mountain Valley Pipeline, from WV into VA. The Sierra Club says the Sabal Trail decision is all they need to force FERC into redoing the EIS’–to force FERC to consider mythical man-made global warming…
    Read More “Sierra Club Radicals Use FL Court Case to Challenge 2 M-U Pipelines”

  • | | | | | | |

    History Made! FERC Overrules NY DEC on Millennium Pipe Permit

    Finally the Federal Energy Regulatory Commission (FERC) has had enough shenanigans from the corrupted New York Dept. of Environmental Conservation (DEC). In a historic, precedent-setting decision, on Friday FERC overruled DEC’s denial of a water permit for Millennium Pipeline’s tiny 7.8 mile pipeline spur from the main Millennium Pipeline to a natural gas power plant under construction in Orange County, NY. On Wednesday, Aug. 30, the DEC issued a denial letter to FERC and Millennium. In it, they claim that FERC’s review of the power plant project (that the pipeline will feed) is deficient based on a recently-decided court case about a pipeline project in Florida (see Corrupt NY DEC Denies Water Permit for 7.8 Mile Power Plant Pipeline). The radicalized DEC used the Florida case as an excuse to refuse stream crossing permits for the Millennium Pipeline project–claiming FERC had not considered long-term effects of mythical man-made global warming that would come from the power plant if the Millennium pipeline is connected to and feeds the plant. The DEC decision was a naked attempt to grab power not given to it under federal law. FERC said ENOUGH, and ruled on Friday the DEC had taken too long (over one year) in dithering with a decision on the Millennium pipeline request. A recent ruling by the U.S. Court of Appeals for the District of Columbia said FERC has the power and authority to overrule the DEC when they take longer than one year to grant permits (see DC Court Tells Millennium FERC Can Override NY DEC Pipeline Delay). So FERC just exercised their federal, court-approved authority and smashed the DEC into the ground. LOVE IT! Of course the humiliated DEC spit and sputtered and said they will likely sue…
    Read More “History Made! FERC Overrules NY DEC on Millennium Pipe Permit”

  • | | | | | | | |

    FERC Greenlights Construction of Atlantic Sunrise Pipeline

    Bad news for the Sisters of the Corn and the radicals at Lancaster Against Pipelines. On Friday the Federal Energy Regulatory Commission (FERC) granted Williams permission to begin construction on Atlantic Sunrise, a $3 billion, 198-mile pipeline project running through 10 Pennsylvania counties to connect Marcellus Shale natural gas from northeastern PA with the Williams’ Transco pipeline in southern Lancaster County. Last week the Sierra Club and a mish mash of other nutball groups begged FERC to delay issuing an order that Williams can commence with construction, claiming FERC’s delay in considering a rehearing delayed a lawsuit and the lawsuit hasn’t had enough time to work it’s way through the court system (see Big Green Begs FERC to Delay Construction of Atlantic Sunrise Pipe). As was expected, Big Green’s begging and pleading fell on deaf ears. Williams previously said they plan to begin construction on Sept. 20th–this Wednesday. Ladies and gentleman, start your (backhoe) engines! Sisters of the Corn (see Lancaster Sisters of the Corn Lose Bid to Stop Atlantic Coast Pipe), you may want to pick up your wooden park benches and the flower trestle–what you call a “chapel”–in the middle of your corn field. Here comes the Atlantic Sunrise!…
    Read More “FERC Greenlights Construction of Atlantic Sunrise Pipeline”

  • | | | |

    Canadian Drillers Beg NEB to Approve Pipe Plan to Compete with M-U

    TransCanada, one of Canada’s leading midstream/pipeline companies, cooked up a deal last year to pipe natural gas from Canada’s West Coast to the East Coast in order to fend off cheap supplies of Marcellus/Utica gas that will flow into Canada when/if the NEXUS and Rover pipelines get built (see TransCanada Pipe Drops Price 42% to Compete with Marcellus/Utica). TransCanada dropped their pipeline price to lure drillers by (theoretically) making it less expensive to get gas from Western Canada, some 2,400 miles away, than from the Marcellus, just 400 miles away. The original open season last year was a bust because TransCanada insists on a 10-year commitment (see TransCanada Plan to Lowball M-U Gas Using Canada Pipeline a Bust). TransCanada revived their plan in February. Although it looked almost like the same deal all over again with the same 10-year term and about the same price, TransCanada dropped a minimum amount to be shipped and is letting shippers opt out after five years under certain conditions. The changes worked (see TransCanada Says Plan to Lowball M-U Gas Worked, Shippers Sign Up). The plan needs a bevy of regulatory approvals, the main one being the Canadian National Energy Board (NEB). The clock is ticking and time is running out. In hearings before the NEB last week, the Canadian Association of Petroleum Producers pleaded their case that the plan get approved. Without it, western Canadian gas simply can’t compete with cheap, abundant Marcellus/Utica Shale gas flowing north. In somewhat dramatic terms, Canadian drillers claimed the “future of western Canada’s natural gas industry could depend on pipeline company TransCanada winning regulatory approval” of their lowball plan…
    Read More “Canadian Drillers Beg NEB to Approve Pipe Plan to Compete with M-U”

  • | | | | |

    19 Radicals Arrested for Blocking DEQ Building in Richmond, Va.

    As MDN told you two weeks ago, radicals from the Chesapeake Climate Action Network (CCAN) said they would stage “massive” protests at several Virginia Department of Environmental Quality offices last week to protest against two Marcellus/Utica pipeline projects: the $5 billion Atlantic Coast Pipeline and $3.5 billion Mountain Valley Pipeline. Both projects have large segments crossing Virginia (see Radical CCAN to Protest VA DEQ Against Marcellus/Utica Pipelines). CCAN said up to 1,000 people would turn up to behave badly at DEQ office sites–using sit-ins, “prayer circles” and sidewalk “rallies.” The so-called “massive” rallies where held–and it was bust. At the main DEQ office in Richmond, “dozens” turned out to protest the pipelines. If it weren’t for the signs and sloppy dress code, you wouldn’t have known they where there–they would have blended in with the crowd. In the end, 19 of the radicals were arrested for blocking an entrance to the building where the DEQ has its office. The news account of the “arrest” of these radicals sounds more like a tea party than a crime scene. One radical said she though the police “were just great”…
    Read More “19 Radicals Arrested for Blocking DEQ Building in Richmond, Va.”

  • | | | | | | |

    Big Green Begs FERC to Delay Construction of Atlantic Sunrise Pipe

    Last week the Pennsylvania Dept. of Environmental Protection (DEP) issued the final permit needed by Williams to begin construction on Atlantic Sunrise, a $3 billion, 198-mile pipeline project running through 10 Pennsylvania counties to connect Marcellus Shale natural gas from northeastern PA with the Williams’ Transco pipeline in southern Lancaster County (see PA Issues Final Permit for Atlantic Sunrise, Construction Sept 20). The only thing left before Williams fires up the bulldozers and backhoes and begins to dig is for the Federal Energy Regulatory Commission (FERC), which has already fully approved the project, to issue a “you can begin building” order. Last week Williams said they hope/plan to receive that order imminently, and begin construction next week, on Sept. 20th. However, the radicals at the Sierra Club and a bunch of other loony leftist “environmental” organizations are riding in to ruin the day. They’ve filed an urgent request with FERC to delay issuing the order to begin building. Why? Because these cancerous groups previously filed a lawsuit in federal court that seeks to have FERC reverse their decision to approve the project. The first step in the process when radical groups challenge a FERC order is for FERC itself to reconsider whether or not to rehear arguments against a project. FERC did delay, using something called a “tolling order.” Because of the tolling order delay, the radicals could not (as they wanted all along) appeal the case to the liberal D.C. Court of Appeals, the next step in the process. The radicals say the now-appealed case before the 2nd Circuit hasn’t had enough time, therefore FERC should delay an order to allow construction to begin for Atlantic Sunrise…
    Read More “Big Green Begs FERC to Delay Construction of Atlantic Sunrise Pipe”