FERC Won’t Extend Atlantic Coast Pipeline Tree Cutting Deadline
Two weeks ago Dominion Energy asked the Federal Energy Regulatory Commission (FERC) for permission to extend tree cutting/felling season by an extra 45 days, from March 31 to May 15, in West Virginia, Virginia and North Carolina (see Atlantic Coast Pipe Asks FERC for More Time to Cut Trees). Due to restrictions for species like the threatened Indiana bat, tree cutting season is limited–from November 16 to March 31. ACP said it couldn’t meet the March 31 deadline due to a late start following state bureaucratic delays. In a presentation Dominion gave to North Carolina environmental officials a few months back, the company said if “we cannot start [pipeline construction] in time to ensure a full and efficient construction season and have to delay service by one year, the impact would be $1 billion.” Dominion maintains that worst case scenario has not yet happened. Following the FERC decision to deny extending the date for tree cutting, Dominion said they’ll shift things around and can still meet their contractual deadline of getting ACP up and running by the end of next year…
Read More “FERC Won’t Extend Atlantic Coast Pipeline Tree Cutting Deadline”


Earlier this month MDN reported that the Southern Environmental Law Center and Appalachian Mountain Advocates, on behalf of a mishmash of second tier radical groups, filed a “hail Mary” request with the federal Fourth Circuit Court of Appeals to stop construction of Dominion Energy’s Atlantic Coast Pipeline until a lawsuit sitting before the Fourth Circuit questioning the validity of the permits granted for the project is played out (see 
“Hey Jim, what’s happening with Cove Point LNG? Didn’t you say a ship was on the way to pick up the very first cargo of Marcellus molecules?” Great question. Cove Point did see its first cargo set sail in early March (see
Dominion Energy’s $6.5 billion Atlantic Coast Pipeline (running from West Virginia through Virginia and into North Carolina) is supposed to get built this year. ACP began to cut trees along the pipeline’s path in late January (see
We’re not quite sure what to make of this story. North Carolina has been, as we’ve long pointed out, nitpicking in an attempt to slow down (or stop) the Atlantic Coast Pipeline (ACP) from traversing the state (see
Big Green groups opposed to Dominion Energy’s $6.5 billion (up from $5 billion due to delays) Atlantic Coast Pipeline (ACP) from West Virginia through Virginia and into North Carolina are about out of options in their holy mission to stop the project. They’ve tried multiple lawsuits, protests, bullying state environmental agencies–the whole bag of nasty tricks. And yet ACP is now under construction. What’s left to try to stop it? The Southern Environmental Law Center and Appalachian Mountain Advocates, on behalf of a mishmash of second tier radical groups, have filed a “hail Mary” request with the Fourth Circuit Court of Appeals to stop construction of ACP until a lawsuit sitting before the Fourth Circuit questioning the validity of the permits granted for the project is played out. In other words, back to the tried-and-true playbook: delay, delay, delay–until eventually you deny…
As MDN reported last Friday, the very first cargo of LNG (liquefied natural gas) left the Cove Point LNG export facility in Lusby, Maryland (see
Earlier this week MDN told you the ship that would carry the very first cargo of LNG from Cove Point LNG had docked (see
Tree clearing for Dominion’s $5 billion Atlantic Coast Pipeline (ACP) has already begun in West Virginia (see
On Monday, Dominion Energy CEO Tom Farrell reported that the company’s Lusby, Maryland Cove Point LNG export facility will become operational and begin to export LNG in “early March” (see
Dominion Energy, a huge company with fingers in many pies (gas and electric utility, electric generator, nuke plant owner, pipeline company, LNG exporter) issued its fourth quarter and full year 2017 update on Monday. Dominion’s top brass also held an earnings call with analysts. We reported yesterday that on the earnings call, Dominion CEO Tom Farrell said the Cove Point LNG export plant on the shore of Maryland will begin shipping LNG “in early March” (see