NEXUS Pipe Goes to Court to Gain Easements on 42 Ohio Properties
NEXUS Pipeline has had to use the unpreferred last option and has taken landowners of 42 properties to court using eminent domain in order to secure easements so they can lay pipeline through those properties. NEXUS is a $2 billion, 255-mile interstate pipeline that will run from Ohio through Michigan and eventually to the Dawn Hub in Ontario, Canada. NEXUS received final approval for the project from the Federal Energy Regulatory Commission (FERC) in August, the first major pipeline to get approved following a newly restored quorum at FERC (see New FERC Quorum Votes Final Approval for NEXUS Pipeline). In early October, FERC gave NEXUS permission to begin construction (see NEXUS Cleared to Begin Construction, Rover Cleared to Restart HDD). While 97% of the landowners along the proposed route have signed easements for the pipeline, a few have not. The landowners NEXUS has taken to court (so far) are in Ohio, in Stark, Summit, Wayne, Medina, Lorain, Sandusky, Wood and Erie counties. Yes, there are still a few lawsuits hanging out there, including a lawsuit by Green, OH and one by the Coalition to Reroute Nexus (CORN). However, it seems unlikely the lawsuits will stop the project. Here’s the unfortunate news about NEXUS suing a few holdouts…
Read More “NEXUS Pipe Goes to Court to Gain Easements on 42 Ohio Properties”

Our heart stopped when we saw news from Crestwood Equity (used to be called Crestwood Midstream) yesterday that the company has sold its US Salt business on the shore of Seneca Lake near Watkins Glen to Kissner Group for $225 million. We thought, “Oh no! Crestwood has finally thrown in the towel on their Seneca Lake Propane Storage project!” But alas, our fears were unfounded. Background: In 2009 Inergy filed a request to convert a depleted salt cavern along the shore of Seneca Lake (in Schuyler County, NY, near Watkins Glen) into a propane/natural gas storage facility. Inergy was later bought by and merged into Crestwood Midstream, and Crestwood Midstream later renamed itself Crestwood Equity Partners. The New York Dept. of Environmental Conservation (DEC) has been sitting on its hands from the beginning, refusing to grant the necessary permits to allow the facility to open. Sound familiar? Same old delay and later deny strategy from our corrupt governor, Andrew Cuomo. As recently as May of this year, Crestwood remained committed to building the storage facility in depleted salt caverns originally drilled by US Salt, which is owned by Crestwood (see
FTS International, is the largest private (not publicly traded stock) well completion company in North America. In 2015 FTS fracked EQT’s ginormous Scotts Run 591340 dry Utica well in Greene County, PA producing an initial production (IP) of 72.9 million cubic feet of natural gas per day (see
The Federal Energy Regulatory Commission (FERC) has just escalated a much-needed war with the CORRUPT, Andrew Cuomo-directed Dept. of Environmental Conservation (DEC) in New York. We won’t recount the entire history, but the DEC had arbitrarily, after more than one year of review, ruled against issuing a federal water crossing permit for a tiny 7.8 mile pipeline Millennium needs to build from its main pipeline to an electric generating plant under construction in Orange County. The power plant is due to be completed in early 2018–and needs a fuel supply. In a monumental decision, FERC overruled NY DEC in September (see
A cabal of three, rabid, radical so-called environmental groups are once again trying to obstruct the legally-permitted Mariner East 2 (ME2) natural gas liquids pipeline project in Pennsylvania. Clean Air Council, THE Delaware Riverkeeper and the Mountain Watershed Association filed a motion with the PA Environmental Hearing Board, a special court set up to hear appeals of decisions made by the Dept. of Environmental Protection, to revoke permits previously issued by the DEP for the ME2 project–WITHOUT holding a trial. The groups are attempting to rush through a decision to block work on the pipeline by claiming there are “facts” in the case “not in dispute” and that the judge can simply take the reigns of justice into his own hands and rule by fiat. The heart of their case is that DEP granted federal water crossing permits for ME2 for “exceptional value” swamps, er, a, wetlands–and ya know, that just ain’t right. Even the attorney for the odious (and odoriferous) Clean Air Council says the judge won’t rule on the motion for at least two months–which is about the time the pipeline will be done anyway. So we’re not quite sure what these rabid groups hope to accomplish with their latest stunt. Perhaps it’s yet another fundraiser? The holidays are fast approaching…
Yesterday midstream and utility giant Dominion Energy issued their third quarter 2017 update. During an analyst phone call, Dominion CEO Thomas Farrell shared some great news regarding both the Cove Point LNG export facility and Atlantic Coast Pipeline (ACP). Farrell said Cove Point will “begin generating LNG” in November, “conclude commissioning” in December and be fully operational by the end of this year. Fantastic! In response to a question by an analyst about Atlantic Coast Pipeline, Farrell said he expects water permits from West Virginia, North Carolina and Virginia will all be issued by the middle of December. Again, fantastic! These two projects are HUGE with respect to the future of the Marcellus/Utica region. Christmas has come early this year. 🙂 Below is yesterday’s 3Q17 update for Dominion, along with the latest slide deck and select comments pulled from the analyst phone call…
Sunoco Logistics has been slapped down in a ruling by the Pennsylvania Public Utility Service (PUC) with respect to a valve station, part of the Mariner East 2 (ME2) pipeline project. In March, MDN told you about an attempt by liberal anti-pipeliners in West Goshen (Chester County) to block the ME2 project (see
Yesterday EQT provided an update for both its drilling and midstream operations. On the midstream side, EQT had an interesting comment about it’s biggest project on the books–the Mountain Valley Pipeline (MVP). MVP is a $3.5 billion, 303-mile natural gas pipeline that will run from Wetzel County, WV to the Transco Pipeline in Pittsylvania County, VA. The Federal Energy Regulatory Commission (FERC) issued a final approval for the project two weeks ago (see
Mountaineer NGL Storage wants to build a new underground NGL storage facility in Monroe County, Ohio, near Clarington, along the Ohio River (see
Yesterday MDN brought you the exciting news that Marcellus shale gas molecules have been/are finding their way all the way to Nova Scotia, Canada (see 
In late September MDN connected the dots and was the first to tell you that Blue Ridge Mountain Resources, the renamed Magnum Hunter Resources, had sold its ownership stake in Eureka Midstream (formerly Eureka Resources) to South Korean conglomerate SK Group (see
Last week NEXUS Pipeline notified the Federal Energy Regulatory Commission (FERC) they had begun construction on the $2 billion, 255-mile interstate pipeline that will run from Ohio through Michigan and eventually to the Dawn Hub in Ontario, Canada. We purposely held off on sharing this exciting news until we could tell you where construction has begun. Each week NEXUS, like other interstate pipelines answering to FERC, provides a weekly update on construction and other project activities. We have a copy of that report (below). What does it show? Preliminary activities are taking place to move equipment, put up signage, and begin to work in “Spread 1”–meaning somewhere within Columbia, Stark, Summit, and Wayne counties in Ohio. Similar work is happening in “Spread 4”–meaning counties in Michigan. Initial site preparation is already happening at three of the four planned compressor stations. Here’s what we have been able to piece together about the initial construction work done on NEXUS…
Two weeks ago MDN brought you analysis from RBN Energy that hints at least some Marcellus/Utica gas molecules are flowing all the way to Cheniere Energy’s Sabine Pass LNG export facility (see
In August Energy Transfer’s Sunoco Logisitics unit struck a deal with the devil–the devil being the Philadelphia-based Clean Air Council, THE Delaware Riverkeeper and Mountain Watershed Association–in a move to lift a ban on underground horizontal directional drilling (HDD) for the Mariner East 2 NGL pipeline project (see