Kentucky Antis File Lawsuit to Stop TGP NGL Pipe Reversal
Kentucky antis have gone to court to try and block a plan by Kinder Morgan to convert a portion of the Tennessee Gas Pipeline that flows natural gas from the Gulf Coast to the northeast, to reverse the pipeline and flow natural gas liquids from the Marcellus/Utica region to the Gulf. Part of the 964-mile project runs through Kentucky (see KM Plans to Convert Tennessee Gas Pipeline to Flow M-U NGLs South). The first step in the reversal process was approved by the Federal Energy Regulatory Commission last October (see FERC Advances Plan to Reverse Part of TGP to Haul M-U NGLs to Gulf). Antis in Kentucky got their bluegrass knickers in a twist over FERC’s action. They filed a request for “rehearing” of FERC’s decision, which is the first step in a process that typically ends up in court. First the “aggrieved party” (antis are in a perpetual state of being aggrieved) must request a rehearing. If FERC denies the rehearing request, antis (Big Green groups with deep pockets representing them) then file a lawsuit in federal Appeals Court to try and stop FERC from continuing to approve the project. Normally FERC has 30 days to decide on a rehearing, however, they have a little tactic they call a “tolling order” which allows them to extend the amount of time to make a rehearing decision–indefinitely. FERC pulled out the tolling order card and played it with the TGP project last November (see FERC Frustrates Kentucky Radicals Seeking to Stop TGP Pipe Reversal). The antis aren’t waiting. They’ve just filed a lawsuit challenging the FERC tolling order. Here’s the latest from the enviro nuts in the Bluegrass State…
Read More “Kentucky Antis File Lawsuit to Stop TGP NGL Pipe Reversal”

In December 2016 MDN brought you news about Kinder Morgan’s “Broad Run Expansion Project” that will expand transportation capacity of natural gas on the existing Tennessee Gas Pipeline (TGP) system. Antis tried to stop the project, but the Federal Energy Regulatory Commission rejected their pleas (see 
What’s in the water in Kentucky? Seems to be a state full of anti-drilling, anti-pipeline nutters. Kentucky has been responsible for killing at least one pipeline, the Bluegrass Pipeline that would have flowed Marcellus/Utica NGLs (natural gas liquids) all the way to the Gulf Coast (see
In October 2015, Kinder Morgan’s Tennessee Gas Pipeline (TGP) filed their official, full application with the Federal Energy Regulatory Commission (FERC) seeking approval for their Orion Project (see
There’s lots of acronyms in that headline, so right up front let us restate the headline in clearer language: The Federal Energy Regulatory Commission (FERC) has just taken the next step to advance a project by Kinder Morgan to reverse a portion of the mighty Tennessee Gas Pipeline (TGP) to reverse its flow, to go from the northeast to the southwest, in order to haul Marcellus/Utica natural gas liquids (NGLs) to the Gulf Coast. Currently TGP hauls natural gas (not liquids) from the Gulf to the northeast. With a bumper crop of natural gas produced by the Marcellus/Utica, gas from the Gulf is no longer needed. Kinder Morgan, the owner/operator of TGP, first floated the idea to reverse 964 miles of their pipeline back in 2013 (see
In April 2015 Kinder Morgan’s Tennessee Gas Pipeline (TGP) subsidiary filed an application with the Federal Energy Regulatory Commission (FERC) to build 8.2 miles of new looping pipeline in Tioga County, PA and beef up two compressor stations in Bradford County, PA. The $142 million project is called the Susquehanna West Project. It will increase capacity along the 300 Line section of TGP, bumping it up by 145 million cubic feet per day (Mmcf/d). All of the extra capacity is spoken for by Statoil and the wells they’ve drilled in NEPA. Last September, FERC approved the project (see
Last week MDN brought you the news that THE Delaware Riverkeeper had lost a federal lawsuit against Kinder Morgan’s Orion Project to expand the Tennessee Gas Pipeline in northeast Pennsylvania (see
In March, Big Green group THE Delaware Riverkeeper (leftist political lobbying arm for the William Penn Foundation that funds it) filed a lawsuit in the U.S. Court of Appeals for the Third District requesting the court overturn a Clean Water Act permit granted by the U.S. Army Corps of Engineers for Kinder Morgan’s Orion Project in northeast Pennsylvania. Yesterday, in a humiliating defeat, the Third Circuit rejected Riverkeeper’s request and ruled the Army Corps was well within its right to grant the permit (full copy of the ruling below). In October 2015, Kinder Morgan’s Tennessee Gas Pipeline (TGP) filed their official, full application with the Federal Energy Regulatory Commission (FERC) seeking approval for the Orion Project (see 
Is Kinder Morgan’s NED pipeline project getting reincarnated?! You may recall that over a year ago, in April 2016, anti-fossil fuel nuts in Massachusetts and other northeastern states were orgasmic that Kinder Morgan announced the company had suspended (not necessarily canceled) any further spending/time/effort on the Tennessee Gas Pipeline expansion from NY through MA, otherwise known as the Northeast Energy Direct (NED) project (see
In March 2016, the Federal Energy Regulatory Commission (FERC) approved Tennessee Gas Pipeline’s (TGP) Connecticut Expansion project (see
In January 2016, Kinder Morgan (KM) committed to building the UTOPIA (Utica To Ontario Pipeline Access) pipeline, a 12-inch ethane pipeline that will run ~240 miles across the state of Ohio where it will connect with another pipeline and (eventually) flow ethane all the way to a cracker plant in Canada (see