Columbia Sues WV Landowners for Delaying Mountaineer XPress Work
It’s one thing for a landowner (or Big Green supporter, sometimes one and the same) to oppose a pipeline project by protesting, asking politicians to get involved, writing to regulatory agencies, etc. We have a great American tradition of free speech. Go for it. But it’s quite another thing to “harass, intimidate and interfere” with work crews in an area by screaming at them and shooting your “large caliber gun” near where they’re working. Columbia Gas Transmission is currently building the Mountaineer XPress Pipeline, a $2 billion, 170-mile pipeline that will flow 2.7 billion cubic feet (Bcf) per day of natural gas from existing and future points of receipt along or near the Columbia pipeline system–most of it located in West Virginia (see Details on Columbia Pipeline Mountaineer XPress Pipeline Project). At 2.7 Bcf/d, Mountaineer XPress is the second largest (by volume) new pipeline project for the Marcellus/Utica region–second only to Rover’s 3.25 Bcf/d pipeline. It is a big and important project. And yet, a single couple whose land the pipeline does NOT cross can delay the entire project with threats and intimidation and interference. That’s the charge Columbia has made in court. On April 30, Columbia sued a couple in Doddridge County who live near an active construction site for Mountaineer XPress, claiming their hostile actions toward workers have caused a delay for the entire project–and that’s costing Columbia big bucks. Columbia wants to ask a jury to extract some of that lost revenue from the hostile couple as compensation. Lesson: Your (hostile, threatening) actions have consequences, and may cost you money…
Read More “Columbia Sues WV Landowners for Delaying Mountaineer XPress Work”


Building and operating a fracking site can emit some airborne particles. But scientists don’t fully understand how many, and how these particles may impact human health. Do drilling operations for unconventional wells emit a lot or a little in the way of particles? And do those particles affect human health? Travis Knuckles, assistant professor at the West Virginia University School of Public Health, has received $450,000 from the National Institutes of Health to investigate these questions. Knuckles will attempt to answer the question, Does fracking impact cardiovascular health–for workers and for those living nearby? We applaud real research efforts like this one…
Mountain V Oil and Gas owns a Marcellus Shale well drilled in 2014 in Upshur County, WV that was a bust. You don’t often hear about Marcellus wells that don’t produce. Because their Marcellus well is a non-producer, Mountain V wants to convert it into a wastewater injection well. The neighbors are not happy about it. The WV Dept. of Environmental Protection held a public hearing last week about the proposal. Twelve local residents spoke at the hearing–every one of them against the project. No one spoke in favor. Is that really a surprise? The comments made at the hearing referred to the potential for earthquakes and pollution of the water table. Here’s what the good (but misinformed) residents of Upshur don’t understand about injection wells: (1) There are hundreds of thousands of them across the country, and have been for decades. (2) The wastewater (brine) going down the proposed injection well first came up from the same deep sources–we’re just putting it back where it came from. (3) If the well is properly cased, and rest assured these wells are heavily regulated and regularly checked, there is no way for the wastewater to seep back up to the surface. The water was down there for millennia and didn’t make its way to the surface, so why would it now? (4) Earthquakes can happen, but only when massive amounts of fluids are injected into an existing fault, or crack, in the rock layers. Earthquakes from injection wells, at least in the northeast, are as rare as hen’s teeth. Look, in all honesty, we wouldn’t be overly thrilled with an injection well locating near us either. However, if you’re going to object, as a first step you need to get your facts straight. Here’s more about last week’s hearing and the lack of facts (and wild statements) that circulated at that meeting…
The Utica Shale is starting to get more love. No, not in Ohio where the play is already well-loved, but in Pennsylvania and West Virginia. Although it’s always been known that the Utica underlies the Marcellus and in fact covers a larger geography than the Marcellus, drillers have not targeted the Utica nearly as much outside of OH. Why? Because it’s nearly twice as deep as the Marcellus and costs more to tap it. The Marcellus is roughly a mile below the surface, and the Utica roughly two miles below. However, there is renewed interest in the Utica in PA and WV in 2018. Most of the Utica wells drilled in PA have, so far, been drilled by Hilcorp. JKLM is targeting the Utica in Potter County. SWEPI (Shell) has drilled a few Utica test wells, as has EQT, CNX and others. Most recently CNX and Seneca Resources mentioned targeting the Utica in their quarterly updates. Throw it all in the mix and what it spells is more Utica drilling on the way in what has, until now, been largely Marcellus country…
In February 2016 there was an accidental release of a hazardous chemical at the MarkWest Energy cryogenic processing plant in Mobley (Wetzel County), WV (see
The radical Sierra Club is claiming a victory in temporarily stopping construction work of the Mountain Valley Pipeline (MVP) at four river crossings in West Virginia. On Tuesday the Sierra Club and a mishmash of other radicalized groups filed a motion asking the Fourth District U.S. Circuit Court of Appeals to suspend a permit issued by the U.S. Army Corps of Engineers that allows MVP to construct the pipeline across streams and rivers in the Mountain State. The Clubbers’ tortured logic is this: When construction of the pipeline across a river, the stated standard is that construction can take no longer than 72 hours. MVP says it will need longer when constructing the pipeline across four rivers–Elk, Gauley, Greenbrier and Meadow. Therefore (say the Clubbers), MVP is in violation of the general permit issued by the Corps and that means ALL (not just those four rivers) construction should be stopped, immediately. The Fourth Circuit has not yet rendered a decision, however, the Corps itself said they had reviewed the standards and have (for now) rescinded the permit as it applies ONLY to those four rivers, NOT to any locations. So it’s a partial, and temporary, victory for the Clubbers…

West Virginia has a long, proud history as a coal producer. And according to West Virginia Coal Association President Bill Raney, some 95% of the electricity produced and used in the Mountain State comes from coal-fired plants. However, natural gas burns cleaner than coal, and frankly, natgas is now cheaper than coal. Yet WV still has not permitted or allowed a single new gas-fired plant to be constructed. Why not? The obvious answer is because Big Coal is pushing back and pushing back hard. Last September WV’s Secretary of Commerce, Woody Thrasher, admitted publicly that his beloved state is unfriendly to new natgas-fired electric plant projects (see
On Friday, the Federal Energy Regulatory Commission (FERC) issued Dominion Energy permission to begin construction of the actual pipeline for the Atlantic Coast Pipeline (ACP) project–in West Virginia. ACP is a (now) $6.5 billion project, up from a projected $5 billion due to delays from regulatory agencies and frivolous lawsuits filed by Big Green groups, that will run from WV through Virginia and into North Carolina–almost to the border with South Carolina. Until now FERC had allowed prep work, like tree cutting. But now actual pipeline construction can begin, which is a momentous occasion, worthy of celebration!…
Despite all of the media attention on a handful of protesters who sit in the tops of trees or on top of a poll in order to block construction of the Mountain Valley Pipeline (MVP), the pipeline nonetheless continues to receive regular new permissions from the Federal Energy Regulatory Commission (FERC) to construct the actual pipeline and (yes), even to cut trees past the March 31 deadline. The good news is that MVP is on track to be completely built and flowing Marcellus/Utica gas by the end of THIS YEAR! Despite the best efforts of radical protesters and multiple lawsuits by Big Green groups. Recent FERC permissions for MVP include: (1) allow MVP to cut trees in Jefferson National Forest past the March 31 deadline; (2) build parts of the pipeline in Roanoke and Franklin Counties, VA; (3) work 24/7 on building a compressor station in Wetzel County, WV; and (4) build pipeline in Jefferson National Forest, on both the VA and WV sides…
The vast majority of Rover Pipeline is done, and most of it is now up and running (see
West Virginia Secretary of Commerce, Woody Thrasher, once again addressed the issue of an ongoing trade war with China at yesterday’s West Virginia Oil and Natural Gas Association (WVONGA) conference at Oglebay Park. Last November Thrasher signed a memorandum of understanding with the Chinese government, an agreement in which the Chinese pledged to spend $83.7 billion over the next 20 years in WV’s shale and petrochemical sectors (see 