Energy Transfer 1Q17 – Updates on Rover, Mariner East 2 Pipelines
Last week Energy Transfer Partners (ETP), the main operating division of Energy Transfer Equity (ETE), released its first quarter 2017 financial and operating update. ETP is the company that built the Dakota Access Pipeline, which was finally completed after Obama was ejected from office–and is right now building the Rover Pipeline. Another division of ETE was, until last month, Sunoco Logistics Partners. In April Sunoco LP was merged into ETP (see Sunoco Logistics Partners Ceases to Exist as of Today). Sunoco LP, now ETP, is building the Mariner East 2 (ME2) pipeline project. So as part of last week’s update, we got mini-updates on two critically important projects for the Marcellus/Utica: Rover and ME2. The Rover chatter indicates all systems are go and they are on track to have the project completed and in-service as far as the Midwest Hub in July, and the rest of the way to Michigan in November. ME2 chatter contained an interesting question and response. An analyst’s question seems to indicate that ETP (the Sunoco Logistics part of it) is considering a joint venture arrangement for the ME2 pipeline project. President & CEO of Sunoco LP (not sure what his title is now) Mike Hennigan was quick to tamp down that speculation. He didn’t deny it, saying the company is having “conversations”–but he did say their focus right now is to finish the darned thing. Get it built…
Read More “Energy Transfer 1Q17 – Updates on Rover, Mariner East 2 Pipelines”

Elise Gerhart has been up a tree before. You may recall our story about Elise, daughter of a Huntingdon County, PA landowner, radicalized by Big Green groups (as evidenced by her association with well known protesters previously arrested), who took to a tree on her mom’s property in order to illegally stop crews working on tree clearing for the Mariner East 2 pipeline (see 
This one has us spitting nails. We have reported, for months, about the activities of so-called protesters against Williams’ $3 billion Atlantic Sunrise Pipeline project. In particular, there is a group in Lancaster County, PA opposing the pipeline creatively called Lancaster Against Pipelines (LAP). Some of their members previously attended and participated in protests against the Dakota Access Pipeline in Standing Rock, ND–protests that turned violent and destroyed millions of dollars in equipment (see 
Yesterday midstream and utility giant Dominion issued its first quarter 2017 update. Along with the update Dominion held an earnings call. On that call we learned new information about both the Atlantic Coast Pipeline (ACP) project, Dominion’s Cove Point LNG export project, and a plethora of other projects, including natgas-fired power plants and more pipelines in the works. Dominion CEO Tom Farrell shared the exciting news that Cove Point is now 89% complete and will be “in service” later this year. As for Atlantic Coast Pipeline, Dominion has now purchased 80% of the materials they will need to build it. Farrell said the pipeline will be online in the second half of 2019. Another six pipeline projects are underway (at a cost of $700 million)–with five of the six due to be done THIS YEAR. Dominion is a happening company. Below are extracts from the earnings call, the 1Q17 update (with financials), and the newest PowerPoint slide deck used during the earnings call…
The U.S. The House of Representatives’ Committee on Energy and Commerce held a hearing on Wednesday to hear testimony on a proposed plan to grant the Federal Energy Regulatory Commission (FERC) more authority to speed up the pipeline approval process. Up for discuss is an amendment to the Natural Gas Act to grant FERC more authority in coordinating what is, admittedly, a complex review process. A more powerful FERC would, for example, likely be able to override states like New York that refuse to grant water crossing permits (permits that are issued under a federal law!). Don Santa, executive director of the Interstate Natural Gas Association of America, was one of the people testifying before the assembled Congressmen. He said things have gotten pretty bad over the past two years–yes with FERC, but also with other federal and state agencies. Here’s some of what was said at the hearing…
Did you know that even with our super-productive fracking methods, we still only pull out an estimated 5% of oil found in shale, and an estimated 20% of natural gas? That’s abysmal! Can’t we do better? Indeed, perhaps we can. Shale oil and gas is locked up in teeny tiny pores in shale rock–very small “pockets” if you want to think of it that way. The reason we don’t currently do a better job of accessing more of those small pockets is lack of understanding in how fluids flow through these small pores, which measure nanometers across. It takes one billion nanometers to make up one meter, or roughly three feet. Exciting new research shared this week in the journal Physics of Fluids sheds new light on the physics of fluids flowing through shale rock. The research paper, “Many-body dissipative particle dynamics modeling of fluid flow in fine-grained nanoporous shales” (full copy below). This new research means we are on the path to learning how to extract even more oil and gas from the same shale rock. Now that’s something to celebrate!…
The City of Green, Ohio, located in Summit County (south of Akron, north of Canton) seems to have no problems with spending boatloads of taxpayer money on anti-pipeline efforts. A few weeks ago Green City Council voted to give $10,000 to the anti-pipeline CORN–Coalition to Reroute Nexus. We call the group CORNballs and have written extensively about their supposed desire to just see the NEXUS pipeline routed around them, pretending to be NIMBYs (
In June 2014, MDN told you about the Dominion New Market Project–a project that will build two new compressor plants and upgrade one other compressor station in upstate New York–to help flow more abundant, cheap and clean-burning Marcellus Shale gas from Pennsylvania (and beyond) into the northeast (see
For years we’ve followed the story of Range Resources and their (former) wastewater impoundments in Washington County, PA. The PA Dept. of Environmental Protection (DEP) fined Range a whopping $4.15 million for violations in September 2014 (see
Westinghouse Electric tried “an ambitious new approach to building nuclear power plants” by building sections of the plants in one location before sending them to the construction site for assembly. They tried the process with two nuke plants–one in Georgia and the other in South Carolina. The process they “innovated” failed and took the company down–into bankruptcy. What does that have to do with the Mariner East 2 (ME2) Pipeline project? Westinghouse Electric is headquartered just outside of Pittsburgh and owns a fair amount of land. Mariner East 2 intends to cross a portion of that land. Sunoco Logistics Partners, builder of ME2, attempted to negotiate a payment for an easement to cross Westinghouse’s land–but Westinghouse wanted more than ME2 offered. So ME2 filed paperwork to use eminent domain and “condemn” the Westinghouse property. In other words, let a judge decide how much is fair. Westinghouse joined the chorus that “ME2 isn’t really a public utility”–sounding no different than the Sierra Club and others who oppose the project. That strategy went nowhere, so Westinghouse eventually came back to the bargaining table and this time, worked out a deal–to sell some of their land to ME2. Now Westinghouse is asking the bankruptcy judge in charge of their case to approve the land sale, ahead of the judge’s decision on other matters to do with the bankruptcy. Here’s an account of the high stakes of “chicken” between Westinghouse and ME2…
More than 300 people attended the West Virginia Manufacturers Association’s Marcellus and Manufacturing Development Conference in Morgantown yesterday. Among the topics discussed–the need for faster approvals of pipelines, and the positive economic of shale on the Mountain State. Among the speakers was new State Commerce Secretary Woody Thrasher–who spent most of his career in the private sector. According to Thrasher, “shale gas is the future of economic opportunity in West Virginia.” Thrasher said the industry with the biggest potential for growth in WV is shale energy–and it’s “only begun to emerge.” He urged audience members to get involved and make their voices heard–at the local, state and federal level. We think it’s a fair statement to say that Thrasher rallied the troops and is leading the charge to see more shale energy developed in WV…
Yesterday Noble Energy dropped a bombshell that it has sold its 100% interest in 385,000 Marcellus/Utica acres and wells producing 415 million cubic feet equivalent of natural gas in West Virginia and Pennsylvania for $1.225 billion to “an undisclosed buyer.” That works out to be $3,181 per acre. Not included in the sale is Noble’s half operating interest in the CONE Midstream pipeline gathering system. It was just three years ago that Noble announced it would lease 138,000 feet in a new office building in Southpointe, and move in 200 employees (see 
Yesterday the five justices of the West Virginia Supreme Court reheard a case involving post-production deductions from royalty payments. Last week we reported that the court *might* rehear the case this week–if they didn’t grant a late-breaking motion to dismiss the rehearing (see