Pipelines

  • | | | | |

    NJ Towns Win Delay for Phase 2 of Garden State Expansion Pipe

    You win some, you lose some. Today we brought you the news that THE Delaware Riverkeeper and other radical groups lost their case opposing the Atlantic Sunrise Pipeline project (see Riverkeeper Lawsuit Against Atlantic Sunrise Tossed by Fed Court). However, the same court, the U.S. Court of Appeals for the Third Circuit, went the other way on a different Williams project. Last August two New Jersey towns sued in federal court, seeking to overturn a decision by the Federal Energy Regulatory Commission (FERC) to approve Williams’ Transco Garden State Expansion pipeline project (see FERC Fights NJ Town Effort to Decertify Garden State Expansion). The project was created to address supply disruptions following Superstorm Sandy in 2012. By upgrading compressor stations and adding a new meter station, the Garden State Expansion project will supply an extra 180 million cubic feet per day (MMcf/d) of natural gas to “a new delivery point on Transco’s existing Trenton Woodbury Lateral pipeline.” Two towns in Burlington County (Bordentown and Chesterfield) where some of the work would be done for Phase 2 of the project filed a lawsuit asking the Third Circuit to overturn FERC’s previous decision to allow the project. They also asked that permits issued by the New Jersey Dept. of Environmental Protection (NJDEP) be revoked. Yesterday the court ruled that NJDEP erred by issuing permits for the project. However, the court ruled that the towns’ challenges to FERC’s order allowing the project lack merit (and were dismissed). So, a partial victory–but still more delays because of the ruling re NJDEP…
    Read More “NJ Towns Win Delay for Phase 2 of Garden State Expansion Pipe”

  • | | | | |

    Responding to Sore Loser Antis re Shale Court Cases

    Blond Boy Crying

    Ever notice how antis get all hot and bothered when they lose a court case? They holler and scream and rant and rave. Some even lay down and roll on the floor like two-year-olds. The refrain is always the same: “The court sided with the natural gas industry!” But that claim is not true. The editorial writers at the Charleston (WV) Gazette-Mail recently penned an editorial that, in so many words, tells antis to grow up. They do an excellent job of pointing out the courts are not siding with the industry, they’re siding with the law. Which is a strange and unfamiliar concept for many snowflake antis who were never told “NO” by their parents…
    Read More “Responding to Sore Loser Antis re Shale Court Cases”

  • | | | | | |

    Rover Pipe Asks FERC to Start Up Final 2 Laterals, for Antero

    We finally come down to the final two lateral pipelines for Rover. The Federal Energy Regulatory Commission (FERC) played a game of hardball with Energy Transfer (ET) over the Rover Pipeline. For months FERC refused to allow four Rover laterals–feeder pipelines to shuttle gas from where it’s produced into the main Rover pipeline–to start up (see FERC Plays Hardball with Rover – Refuses to Certify 4 Laterals). The reason? ET had not, according to FERC, lived up to its word on restoration work. Things like smoothing over the dirt and replanting grass/other vegetation over top of the buried pipeline. In early August ET assured FERC it would have the majority of restoration work done on two key laterals–the Burgettstown Lateral in southwestern PA, and the Majorsville Lateral in the northern panhandle of WV–by the end of August. FERC made ET sweat. Finally, near the end of August, FERC gave ET permission to start up both the Burgettstown and Majorsville Laterals on Sept. 1 (see FERC Finally Approves 2 Key Rover Pipeline Laterals, Sept 1 Start). That leaves just two final laterals, the CGT (Columbia Gas Transmission) and Sherwood Laterals, still not online. On Friday ET asked FERC to approve the startup for those two laterals, along with a compressor station and two meter stations associated with them. The driller with the most at stake in the startup of these two final laterals is Antero Resources…
    Read More “Rover Pipe Asks FERC to Start Up Final 2 Laterals, for Antero”

  • | | | | | |

    How MarkWest Gets Marcellus/Utica NGLs to Market

    The Marcellus and Utica Shale layers in Southwestern Pennsylvania, northern West Virginia and eastern Ohio produce a boatload of NGLs–natural gas liquids. One company had the foresight to plan a strategy to separate, transport and sell those NGLs. That company was MarkWest Energy, now known as MPLX following a purchase by/merger into Marathon Petroleum. MarkWest’s plan is firing on all cylinders. The experts at RBN Energy have analyzed MarkWest’s initial strategy, now largely complete, and their long-term strategy, still in the works, to give us a great snapshot of how NGLs are moving from our region to Midwestern and Canadian markets…
    Read More “How MarkWest Gets Marcellus/Utica NGLs to Market”

  • | | | | | | |

    MVP 2nd Big Win This Wk – 4th Circuit Lifts Stay of Water Permit

    As we reported yesterday, EQT Midstream’s Mountain Valley Pipeline (MVP) got some excellent news–that the Federal Energy Regulatory Commission had lifted a stop-work order on the project (see FERC Lifts Mountain Valley Pipe Stop-Work Order, Rehiring). However, two clouds remain over the project, both created by the Fourth District U.S. Circuit Court of Appeals in response to lawsuits from the Sierra Club. One of those clouds is from the Fourth Circuit overturning permits issued by the U.S. Forest Service and Bureau of Land Management that allows MVP to cross 3.5 miles of Jefferson National Forest in West Virginia and Virginia (see Court Cancels Permits for Mountain Valley Pipe on Fed Land). EQT is working on resolving the issue so that USFS and BLM can reissue permits that will pass muster with the court. The other cloud appeared when the Sierra Club convinced the Fourth Circuit to suspend a permit issued by the U.S. Army Corps of Engineers that allows MVP to construct the pipeline across streams and rivers in the West Virginia. The Clubbers got the court to suspend stream and river crossings based on a technicality–that MVP could not, in the case of four river crossings, get the work done within the 72 hour period stipulated by the permit. Therefore the court suspended work at all 591 stream/river crossings the pipeline traverses in WV (see Sierra Club Succeeds in Delaying MVP Project in WV via Court Order). In early July, the Army Corps reworked and reinstated the permit as it applies to the four river crossings in question (see Army Corps Engrs Reinstates MVP Permits for 4 WV River Crossings). The good news is that the Fourth Circuit has granted a motion by the Army Corps to reinstate its permits for all stream/river crossings for MVP. Sunlight is breaking through!…
    Read More “MVP 2nd Big Win This Wk – 4th Circuit Lifts Stay of Water Permit”

  • | | | | | |

    Fayette County, WV Loses Court Case to Block MVP Compressor Stn

    Sometimes counties (and local towns) try to seize power that’s not theirs constitutionally. Particularly when they’re led by liberal Democrats who like to arbitrarily make up their own oil and gas regulations. Such is the case in Fayette County, WV. Most oil and gas regulation is done at the state level–it is a state function. Unless it’s a pipeline that crosses several states. Those projects are regulated at the federal level, to protect citizens in neighboring states from arbitrary and capricious actions (like those New York is engaged in). Counties don’t get to decide whether or not to allow an injection well, or a pipeline. Yet the lib Dems in Fayette believe they can make those decisions. And now, for the second time in two years, a federal court has slapped them down. Two time losers. In August 2017, Fayette County lost a federal court case to block injection wells in the county (see Fayette County, WV Loses Appeal to Block Injection Well). On Wednesday, the three lib Dem commissioners of Fayette lost a second court case–this one an attempt to block a Mountain Valley Pipeline compressor station. Both lawsuits, last year and this year, were aimed at stopping EQT projects…
    Read More “Fayette County, WV Loses Court Case to Block MVP Compressor Stn”

  • | | | | |

    Free Pipeline Worker Training Program Begins Sept. 24 in OH

    The Gas Technology Institute (GTI) continues to offer its popular 100% free training program (worth $3,500) for those interested in a career building pipelines in the Marcellus/Utica region. Starting salaries often exceed $40,000 per year, and a six-figure income is attainable for employees with time and experience. Companies supporting the GTI program have told GTI they anticipate hiring 1,100+ workers over the next two years. There’s no excuse! If you want a high-paying job, get the 4-week training and get yourself to work. Because of ongoing construction programs within the utility and pipeline industry, and because of aging workforce retirements, the M-U pipeline industry has an acute need for reliable gas pipeline workers. The next round of free training, limited to 20 students per section, begins on Sept. 24 at Belmont College in St. Clairsville, OH…
    Read More “Free Pipeline Worker Training Program Begins Sept. 24 in OH”

  • | | | | | | |

    NY Antis Gear Up to Oppose Zero-Emission Compressor Stn

    As we reported in March, Empire Pipeline, the midstream (pipeline) subsidiary of National Fuel Gas Company, filed an application with the Federal Energy Regulatory Commission (FERC) to build two new compressor stations along the Empire Pipeline–one in Tioga County, PA, the other in Ontario County, NY (see Empire Pipe Plans 2 Compressors in PA & NY to Move Marcellus Gas). Without building any new pipeline, the addition of these two compressor stations will allow an extra 205,000 dekatherms per day (205 million cubic feet/day) of PA Marcellus gas to flow through the Empire Pipeline system. The project, called Empire North Project, will provide much-needed natural gas for Upstate NY and Canada. It will also connect to the Tennessee Gas Pipeline, so who knows? Maybe some Marcellus molecules will find their way into New England too. Anti-fossil fuelers in NY are ramping up to oppose the project. Nothing new about that, unfortunately. The thing is, the proposed compressor station in Ontario County will have zero (yes, zero) emissions. It will use electricity instead of diesel or natural gas or other fuels–so there’s no smoke stack and absolutely nothing going into the atmosphere. Completely benign. And yet, because the compressor station will flow more “fracked gas” from PA flow through the pipeline, irrational nutjobs are opposing it. Talk about stupid. These people will protest and oppose an emissions-less compressor station that helps flow more natural gas, but they won’t actually give up their own natural gas! They won’t stop grilling with natural gas. They won’t stop heating and cooking with natural gas. They won’t stop cooling with natural gas. They won’t stop buying clothes and shoes made, in part, from natural gas (plastics). No. Everyone else has to do those things–not these ignorant, wine-tasting snobs from the Finger Lakes who want to block this emissions-less compressor station…
    Read More “NY Antis Gear Up to Oppose Zero-Emission Compressor Stn”

  • | | | |

    FERC Lifts Mountain Valley Pipe Stop-Work Order, Rehiring

    Some good news to lighten your Thursday. The Federal Energy Regulatory Commission (FERC) issued an order yesterday allowing Mountain Valley Pipeline (MVP) to restart work on virtually all of the 303-mile project–everywhere but 28.5 miles in and around the pipeline’s path through Jefferson National Forest (about 9% of the total). On August 3, FERC told MVP to stop all construction, prompted by an order from the U.S. Court of Appeals for the Fourth Circuit vacating permits issued for the project as it crosses 3.5 miles of Jefferson National Forest in West Virginia and Virginia (see FERC Shuts Down ALL Work on Mountain Valley Pipeline in WV, VA). Two weeks later FERC partially lifted the stop-work order, allowing MVP to work on 77 of its 303 miles–about 25% (see FERC Lets MVP Restart Work on 25% of Pipe; MVP Lays off ‘Thousands’). Because of the stop-work order, MVP had to lay off nearly half of the 6,000 workers actively working on the project. A serious blow. With this restart, MVP says they will bring back “a significant amount of workers” who had been laid off. In typical, predictable fashion, both of the Democrat FERC commissioners, Cheryl LaFleur and Dick Glick, said they don’t want construction to resume on the project…
    Read More “FERC Lifts Mountain Valley Pipe Stop-Work Order, Rehiring”

  • | | | | | | | |

    PA Supreme Court Victory for ME2 Pipeline re Two Zoning Cases

    Two different townships in the Philadelphia area, amped-up by and using money from Big Green groups like THE Delaware Riverkeeper (aka Maya van Rossum), tried to stop Sunoco Logistics Partners’ Mariner East 2 (ME2) pipeline project by claiming it violated local zoning ordinances. The construction of ME2 is governed by the PA state Public Utility Commission and the state Dept. of Environmental Protection. It is not a federal (i.e. FERC) project. Because it is a state-oversight project, the issue of primacy (whose rules and regulations govern) resides at the state level and not at the local level. Two local townships–one in Chester County the other in Delware County–argued in separate cases before PA Commonwealth Court that local zoning regulations for siting the pipeline should still apply. Commonwealth Court, in a pair of decisions earlier this year, ruled against that view (see PA Town Loses Appeal to Block ME2 Pipe with Local Zoning Ordinance and PA Appeals Court Rules ME2 Pipe NOT Under Local Zoning). Using Big Green money, both towns appealed their cases to the PA Supreme Court. On Tuesday, the Supremes declined to hear either case, meaning the Commonwealth Court ruling stands and this issue is now, finally, done. Antis’ attempts to stop the ME2 project by using local zoning ordinances is a closed door…
    Read More “PA Supreme Court Victory for ME2 Pipeline re Two Zoning Cases”

  • | |

    List of 16 Major Pipeline Projects Planned for the Northeast

    Did you know there are 16 major, announced pipeline projects in the northeast?! We recently happened across a handy list of those projects, a list published by the Northeast Gas Association less than a month ago. The list includes a description of what will get built, who’s doing the building, and the target in-service date. A few of the projects are in limbo (Constitution, Access Northeast), but most are either under construction or soon will be. We dig this kind of list–well laid-out, concise, and useful. And we think you will too. Here’s the name of the pipelines in the list: Access Northeast, Atlantic Bridge, Atlantic Sunrise, Constitution, Eastern System Upgrade, Empire North Expansion, Northeast Gateway, Northeast Supply Enhancement, Northern Access, PennEast, Portland XPress, Rivervale South to Market, Station 261, Wright Interconnect, Valley Lateral Project. Click to view the list, with full details…
    Read More “List of 16 Major Pipeline Projects Planned for the Northeast”

  • | | | | |

    Massachusetts Throws Up Roadblocks for Pipeline Expansion

    Massachusetts is throwing up more roadblocks and hoops in order to slow down (stop?) a Kinder Morgan project to expand capacity of its Tennessee Gas Pipeline (TGP) in the Springfield, Ma. area. Columbia Gas of Massachusetts and Holyoke Gas and Electric have both requested more natural gas from TGP. They need it, desperately. Kinder Morgan’s solution is to expand the delivery capability of the pipeline in the region by adding a minuscule 2.1 miles of new looping pipeline (buried next to an existing TGP pipe), upgrading a compressor station, and building a new connection, called a delivery gate. It’s a minimal project, and yet Massachusetts has just ruled Kinder will have to conduct a months (years?) long, full-blown environmental impact statement before they can do the work. Which we find strange. TGP is a federal, not state, regulated pipeline. TGP plans to file an application for the project, known as the “261 Upgrade Project” (named after Compressor Station 261), with the Federal Energy Regulatory Commission in September. Massachusetts does not have jurisdiction over the building of the project! Yet they are demanding an environmental impact study. If we were TGP, we’d tell Mass. to get lost…
    Read More “Massachusetts Throws Up Roadblocks for Pipeline Expansion”

  • | | | |

    NJ Rate Counsel Asks Fed Court to Overturn PennEast Pipe Approval

    Using taxpayer’s money, the New Jersey Division of Rate Counsel, an “independent” state agency that supposedly represents the interests of consumers of electric, natural gas, water/sewer, telecommunications, cable TV service, and insurance (residential, small business, commercial and industrial customers), has sued the Federal Energy Regulatory Commission (FERC) in federal court asking the court to overturn FERC’s approval of the PennEast Pipeline, a $1 billion, 120-mile natgas pipeline that will stretch from northeast PA to the Trenton, NJ area. Most of PennEast is located in PA, but the pipeline terminates and flows gas into NJ. The Rate Counsel appears to be a rogue agency using taxpayer’s money to try and defeat a project that will benefit those very taxpayers. NJ residents pay some of the highest taxes in the country. Now we know why…
    Read More “NJ Rate Counsel Asks Fed Court to Overturn PennEast Pipe Approval”

  • | | | | | | |

    FERC Approves Mountaineer XPress Pipe Rate Increase

    We spotted a story that contains information we don’t fully understand. Columbia Gas Transmission is currently building the Mountaineer XPress Pipeline, a $2 billion, 170-mile pipeline that will flow 2.7 billion cubic feet (Bcf) per day of natural gas from existing and future points of receipt along or near the Columbia pipeline system–most of it located in West Virginia (see Details on Columbia Pipeline Mountaineer XPress Pipeline Project). At 2.7 Bcf/d, Mountaineer XPress is the second largest (by volume) new pipeline project for the Marcellus/Utica region–second only to Rover’s 3.25 Bcf/d pipeline. It is a big and important project. When Columbia (aka TransCanada) filed the original application, approved by the Federal Energy Regulatory Commission, they sought permission to charge $9.827 per dekatherm (one dekatherm is equivalent to one thousand cubic feet, or 1 Mcf) to flow gas along the pipeline. Put another way, shippers without a contract who want to ship along the pipeline will pay $9.83/Mcf to ship gas. Since gas typically fetches less than $3/Mcf, how can you make any money? That’s what we can’t figure out. Perhaps one of our sharp MDN readers can enlighten us? MDN Note: We have THE BEST readers! Dmitry Brown, a Senior Analyst with UGI Energy Services, wrote to clear up our confusion. The prices are per month, not per day. Shippers on MXP were expecting to pay $9.827/Mcf/month, or $ 0.32/Mcf/day. Columbia recently filed a request with FERC to increase the charge from $9.83/Mcf to a whopping $14.66/Mcf! The reason, according to Columbia, is that project costs have ballooned from $2 billion to $3 billion, “related to contractor labor costs, inspection costs, and outside services costs that substantially exceeded the contingency established for such charges.” Last Friday FERC approved the 49% increase. Now shippers will have to pay $14.663/Mcf/month, or $0.48/Mcf/day. Quite an increase…
    Read More “FERC Approves Mountaineer XPress Pipe Rate Increase”

  • | | | | | |

    Atlantic Sunrise Pipeline Slightly Delayed, Ready by Sept 10

    In July MDN told you that Williams said their $3 billion Atlantic Sunrise Pipeline that runs through 10 Pennsylvania counties to connect Marcellus Shale natural gas from northeastern PA with the Williams’ Transco pipeline in southern Lancaster County will go online in August (see Williams: Atlantic Sunrise Pipeline Going Online in August). At the time, we said this: “We have no reason to doubt Williams. After all, if they make an announcement like that and then don’t live up to it, there will be PR hell to pay.” Oops. Looks like it’s time for Williams to pay PR hell. Last Friday Williams filed an official request with the Federal Energy Regulatory Commission (FERC) to begin flowing gas along the rest of Atlantic Sunrise beginning Sept. 10. Yeah, it’s only 10 days late, and perhaps close enough that we can forgive them. It is exciting! We’ve waited years to announce the beginning of Atlantic Sunrise flows–amidst protests from nuns, kooks and quacks. Most of the time we think of Atlantic Sunrise as the new greenfield pipeline that cuts through 10 northeastern PA counties, traveling from Susquehanna County to Lancaster County. But that part of the project, called the  Central Penn Line, is only part of the project. Other parts of the larger Atlantic Sunrise project were actually up and running a year ago around this time (see Williams Atlantic Sunrise Project to Begin Partial Service on Sept 1). What will happen Sept. 10 is the completion of those parts of the project not yet online, including the Central Penn Line…
    Read More “Atlantic Sunrise Pipeline Slightly Delayed, Ready by Sept 10”

  • | |

    Marcellus Gas Heads to Florida Electric Power Plants

    Sabal Trail Pipeline route – click for larger version

    Do you know which of our 50 states (57 states if you’re Obama) generates the most electricity? It’s Texas! How about the state that generates the second highest amount of electricity? That would be Florida. California, our most populous state (maybe not anymore now that it’s run by lib Dems) is not in the top 2 for electric generation. Over the past few years, Florida has been dumping coal generating plants and instead building new natural gas-fired electric generating plants. Traditionally Florida has sourced its natgas from the Gulf Coast, but increasingly they now get their natural gas from–yep–the Marcellus/Utica. Say what? That’s right! How does our gas get all the way to Florida? Pipelines, of course. Specifically, Williams flows our gas south along the mighty Transco Pipeline. Marcellus gas volumes along the Transco are about to increase dramatically as the Atlantic Sunrise project comes online (see today’s story about the rest of Atlantic Sunrise going online Sept. 10). Our gas flows south on Transco to a point in Alabama where Transco connects with the Sabal Trail Pipeline–and Sabal Trail goes all the way to the Orlando area. RBN Energy does a deep dive into how our gas gets to Florida in a 2-part series. Below is part one…
    Read More “Marcellus Gas Heads to Florida Electric Power Plants”